Difference between revisions of "Dec 5, 2011 SiPM Electrical and Cooling"
From GlueXWiki
(→Minutes) |
|||
Line 20: | Line 20: | ||
== Minutes == | == Minutes == | ||
− | ''Attending: | + | ''Attending: Jim, Elton, Nic, Jim, Ivan, Yi, Chris |
# Announcements | # Announcements | ||
Line 30: | Line 30: | ||
##* Will check that tooling does the job and start some dry tests before starting. If necessary make any modifications to procedures/setup. | ##* Will check that tooling does the job and start some dry tests before starting. If necessary make any modifications to procedures/setup. | ||
## Bcal assemblies (mechanical) | ## Bcal assemblies (mechanical) | ||
+ | ##* List and sequence of pre-assembly tasks was generated by Elton, Chris, Nic and Jim following the meeting proper (see next) | ||
+ | ##* A better estimate for total time to complete the pre-assembly tasks is needed. However, it clearly needs dedicated manpower next month to complete the tasks by February | ||
+ | ## List of mechanical pre-assembly tasks | ||
+ | ### Fabricate Tubing Assembly (Note: fixturing is complete but not tested) | ||
+ | ###* Cut | ||
+ | ###* Braze fittings onto tube | ||
+ | ###* Bend tube | ||
+ | ###* leak test fittings | ||
+ | ### Gluing | ||
+ | ###* glue tube into cooling plate | ||
+ | ###* glue thermistor onto boards | ||
+ | ###* glue RTD assembly. (Note: Chris needs to provide RTDs with wires soldered already) | ||
+ | ###* install 2 tube clamps onto plate | ||
+ | ### Assemble/sort | ||
+ | ###* insert threaded rods into spacers | ||
+ | ###* sort hardware into labeled bins for use during assembly | ||
# mini-Bcal (Elton) | # mini-Bcal (Elton) | ||
# SiPM production testing (Yi) | # SiPM production testing (Yi) |
Revision as of 17:24, 6 December 2012
Action Items from previous meetings
-
Decide on cable connections for monitoring cable from Bcal wedge to patch panel. Consider electronics needed for pulsing system (Elton and Fernando)Decided to have a separate patch panel, which allows decisions on these other items to a later date -
Make a metal die to punch holes in cooling mat to ease assembly. (Nick and Jim) -
Give Jim a U-board with defective SiPM for devising extraction tool (Nick and Yi) -
Determine granularity of LED bias and power, as well as multiplicity of trigger signals (Elton) -
Check on official releases of the 3D model (Elton and Jim)All items will have a drawing. 3D models will be tagged in directories on the group disk.
Tentative Agenda
- Announcements
- Action Items
- Schedule for production and testing (all)
- mini-Bcal (Elton)
- SiPM production testing (Yi)
- Mechanical assembly (Jim)
- Temperature compensation (Jack)
- Electronic boards (Fernando and Chris)
- Light guide gluing setup (Scot)
Minutes
Attending: Jim, Elton, Nic, Jim, Ivan, Yi, Chris
- Announcements
- Action Items
- Schedule for production and testing (all)
- Light guides
- Approximately 1400 have been delivered and 400 more arrived today.
- Manpower for the gluing has been identified, but will start the week before the break
- Will check that tooling does the job and start some dry tests before starting. If necessary make any modifications to procedures/setup.
- Bcal assemblies (mechanical)
- List and sequence of pre-assembly tasks was generated by Elton, Chris, Nic and Jim following the meeting proper (see next)
- A better estimate for total time to complete the pre-assembly tasks is needed. However, it clearly needs dedicated manpower next month to complete the tasks by February
- List of mechanical pre-assembly tasks
- Fabricate Tubing Assembly (Note: fixturing is complete but not tested)
- Cut
- Braze fittings onto tube
- Bend tube
- leak test fittings
- Gluing
- glue tube into cooling plate
- glue thermistor onto boards
- glue RTD assembly. (Note: Chris needs to provide RTDs with wires soldered already)
- install 2 tube clamps onto plate
- Assemble/sort
- insert threaded rods into spacers
- sort hardware into labeled bins for use during assembly
- Fabricate Tubing Assembly (Note: fixturing is complete but not tested)
- Light guides
- mini-Bcal (Elton)
- SiPM production testing (Yi)
- Mechanical assembly (Jim)
- Temperature compensation (Jack)
- Electronic boards (Fernando and Chris)
- Light guide gluing setup (Scot)