Difference between revisions of "MIT/FutureGrid Data Challenge 2 Production"
From GlueXWiki
Line 3: | Line 3: | ||
== Resources == | == Resources == | ||
* [[ Openstack_at_MIT_Overview | MIT Reuse Cluster ]] providing 17 blades x 8 = 136 cores currently. | * [[ Openstack_at_MIT_Overview | MIT Reuse Cluster ]] providing 17 blades x 8 = 136 cores currently. | ||
− | * [https://www.futuregrid.org FutureGrid] project currently providing us with ~ | + | * [https://www.futuregrid.org FutureGrid] project currently providing us with ~200 cores at various sites: |
** University of Chicago | ** University of Chicago | ||
** Indiana University | ** Indiana University |
Revision as of 11:30, 4 April 2014
Resources
- MIT Reuse Cluster providing 17 blades x 8 = 136 cores currently.
- FutureGrid project currently providing us with ~200 cores at various sites:
- University of Chicago
- Indiana University
- UC San Diego
- University of Texas - Austin
- VMs launched using tools developed with the FutureGrid project using OpenStack technology, exploring the distributed cloud computing model.
Monitoring
- All VMs monitored via Ganglia at http://reuse37.lns.mit.edu
Update 3/28/14
- Running smoothly for the last week with 300+ cores
- Only running jobs for 9001 thus far:
- ~5K jobs complete with 25K events each -> ~125M events produced in 1 week
- May get access to ~100 more cores on FutureGrid
- Will run jobs for 9002 and 9003 on those and/or adjust some of the nodes currently in use
Update 4/14/14
- Some (monthly) maintenance on FutureGrid sites this past week slowed us down a bit.
- We're up to a total of 344 cores now, running both 9001 and 9002.
- Possibility of ~100 more next week. will run 9003 on these, or switch some of the current VMs.