August 14, 2014 FDC+CDC meeting
Agenda
- DAQ (Beni)
- CDC status (Mike, Beni)
- noise studies no ground,with ground
- FDC status (Lubomir)
- Electronics (Chris, Nick)
- Engineering (Bill)
- Chiller
- Cathode scan [1] (Luke)
- Commissioning Wiki Page, FDC commissioning plan (all)
- Other
Instructions for Bluejeans meeting connection
FDC meeting ID: 290664653
Minutes
Participants: Curtis, Naomi(CMU), Sean (NU), Bill, Luke, Mike, Chris, Simon, Beni, Fernando and Lubomir (JLab).
CDC update
- Beni installed a wide grounding braid connecting in a chain all HV boards in one sector (#4)