Difference between revisions of "Photon Beam Commissioning Discussion Oct 15, 2014"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
Line 19: | Line 19: | ||
# Announcements | # Announcements | ||
# ARR3 Recommendations | # ARR3 Recommendations | ||
− | #* | + | #* All recommendations complete and request for operation has been sent to Patrizia |
# Accelerator and Hall D Interface Document - update | # Accelerator and Hall D Interface Document - update | ||
# Update on Photon Commissioning (Alexandre) | # Update on Photon Commissioning (Alexandre) |
Revision as of 07:26, 15 October 2014
Organization
- Time: 4:00 pm EST
- Connecting: detailed instructions are here
- H.323 ip address: 199.48.152.152
- web browser: https://bluejeans.com/536076821
- phone: 408-740-7256 or 888-240-2560
- Conference id: 536076821
References
Action Items
- Estimate rates and ranges of parameters needed for the photon beam tuning (Todd for accelerator; Eugene, Alexandre for Hall D)
- Need rates for profiler, start counter, ps
- Complete the tagger drawing with the expected configuration for the fall running, including all shielding. (Tim, Chuck, Elton)
Agenda
- Announcements
- ARR3 Recommendations
- All recommendations complete and request for operation has been sent to Patrizia
- Accelerator and Hall D Interface Document - update
- Update on Photon Commissioning (Alexandre)
- Beam Simulations
- RadCon update
- Checklists
- Other business
Minutes
"Attending: