− | #* Accelerator Schedule: | + | #* Accelerator Schedule: Weekend: beam to dumplet, Monday morning: lock up Hall D/tagger, evening tune beam to dump, Tuesday: CW to tagger dump, Wed morning: insert radiator |
# ARR3 Recommendations | # ARR3 Recommendations | ||
#* All recommendations complete and request for operation has been sent to Patrizia | #* All recommendations complete and request for operation has been sent to Patrizia | ||
+ | #* Final documentation on the completion of items needed for Javier. | ||
+ | #* RadCon will tag the completed shielding in the tagger area with a plaque. The completion will be confirmed to Eugene | ||
+ | #* Fanning has sent a confirmation of all safety items checked during the walkthrough last Thursday | ||
# Accelerator and Hall D Interface Document - update | # Accelerator and Hall D Interface Document - update | ||
# Update on Photon Commissioning (Alexandre) | # Update on Photon Commissioning (Alexandre) | ||
+ | #* small changes to the plan are being implemented including the last links | ||
+ | #* Tentative proposal to start shifts: standby shifts on Tue evening/night, start regular shifts on Wed day shift | ||
+ | #* Need to take baseline rates of profile monitor before commissioning starts. Hovanes will do this. | ||
+ | #* Eugene: Need checklists before starting various plans. Alexandre: There are checklists for the electron beam and photon beam separately | ||
# [[Beam Simulations]] | # [[Beam Simulations]] | ||
# RadCon update | # RadCon update | ||
+ | #* Note: shielding is being added to the gap in the wall nearest to the dump by Tom's crew | ||
#* Checklists | #* Checklists | ||
# Other business | # Other business |
Revision as of 17:05, 15 October 2014
Organization
- Time: 4:00 pm EST
- Connecting: detailed instructions are here
- H.323 ip address: 199.48.152.152
- web browser: https://bluejeans.com/536076821
- phone: 408-740-7256 or 888-240-2560
- Conference id: 536076821
References
Action Items
- Estimate rates and ranges of parameters needed for the photon beam tuning (Todd for accelerator; Eugene, Alexandre for Hall D)
- Need rates for profiler, start counter, ps
- Complete the tagger drawing with the expected configuration for the fall running, including all shielding. (Tim, Chuck, Elton)
Agenda
- Announcements
- ARR3 Recommendations
- All recommendations complete and request for operation has been sent to Patrizia
- Accelerator and Hall D Interface Document - update
- Update on Photon Commissioning (Alexandre)
- Beam Simulations
- RadCon update
- Checklists
- Other business
Minutes
"Attending: Elton, Beni, Alexandre, Hovanes, Eugene (Hall D); Todd (CASA); Pavel (RadCon); Curtis (CMU); Richard (UConn).
- Announcements
- Accelerator Schedule: Weekend: beam to dumplet, Monday morning: lock up Hall D/tagger, evening tune beam to dump, Tuesday: CW to tagger dump, Wed morning: insert radiator
- ARR3 Recommendations
- All recommendations complete and request for operation has been sent to Patrizia
- Final documentation on the completion of items needed for Javier.
- RadCon will tag the completed shielding in the tagger area with a plaque. The completion will be confirmed to Eugene
- Fanning has sent a confirmation of all safety items checked during the walkthrough last Thursday
- Accelerator and Hall D Interface Document - update
- Update on Photon Commissioning (Alexandre)
- small changes to the plan are being implemented including the last links
- Tentative proposal to start shifts: standby shifts on Tue evening/night, start regular shifts on Wed day shift
- Need to take baseline rates of profile monitor before commissioning starts. Hovanes will do this.
- Eugene: Need checklists before starting various plans. Alexandre: There are checklists for the electron beam and photon beam separately
- Beam Simulations
- RadCon update
- Note: shielding is being added to the gap in the wall nearest to the dump by Tom's crew
- Checklists
- Other business