+ | * Trigger Commissioning Plan | ||
+ | :# Integrate PS trigger to the global DAQ (1 - 2 days) | ||
+ | :# Tune trigger parameters (trigger threshold scans, tune timing offsets) and study performance for | ||
+ | ::: - FCAL (2 days) | ||
+ | :::: Performed threshold scans for noise/cosmic runs [[https://logbooks.jlab.org/entry/3328066 Log entry]] | ||
+ | ::: - BCAL (1 day) | ||
+ | ::: - FCAL & BCAL (1 day) | ||
+ | ::: - ST and TOF (1 day) | ||
+ | ::: - Coincidence of FCAL/BCAL and ST/TOF (2 days) | ||
+ | ::: - Multiple triggers in the system (2-3 days) | ||
+ | :::: Trigger hit-pattern is written to the trigger record | ||
+ | *Trigger Monitoring | ||
+ | |||
+ | : [[Media:trig_gui.png | Trigger Rates]] | ||
+ | |||
+ | : [[Media:fcal_scalers.png | Sub-detector scalers]] | ||
+ | |||
+ | :: - Use config files to initialize electronics modules |
Revision as of 09:39, 6 April 2015
- Trigger Commissioning Plan
- Integrate PS trigger to the global DAQ (1 - 2 days)
- Tune trigger parameters (trigger threshold scans, tune timing offsets) and study performance for
- - FCAL (2 days)
- Performed threshold scans for noise/cosmic runs [Log entry]
- - BCAL (1 day)
- - FCAL & BCAL (1 day)
- - ST and TOF (1 day)
- - Coincidence of FCAL/BCAL and ST/TOF (2 days)
- - Multiple triggers in the system (2-3 days)
- Trigger hit-pattern is written to the trigger record
- - FCAL (2 days)
- Trigger Monitoring
- - Use config files to initialize electronics modules