m |
||
Line 8: | Line 8: | ||
# Accelerator Status | # Accelerator Status | ||
#* Beam was mostly stable but with some increase in the trip frequency overnight [https://logbooks.jlab.org/files/2017/02/3460071/Screenshot-Chart%20%232--%20Strip.png] [https://logbooks.jlab.org/entry/3460070] | #* Beam was mostly stable but with some increase in the trip frequency overnight [https://logbooks.jlab.org/files/2017/02/3460071/Screenshot-Chart%20%232--%20Strip.png] [https://logbooks.jlab.org/entry/3460070] | ||
+ | #** Apparently, to turn on/off Hall A beam, our beam has to be taken down as well for a few minutes | ||
#** 2 downtime incidents of more than 30 minutes: | #** 2 downtime incidents of more than 30 minutes: | ||
#*** Continuation of 1L23 issue from the previous day (1.5 hrs) [https://logbooks.jlab.org/entry/3459691] | #*** Continuation of 1L23 issue from the previous day (1.5 hrs) [https://logbooks.jlab.org/entry/3459691] | ||
Line 17: | Line 18: | ||
#* In the last 24 hours: | #* In the last 24 hours: | ||
#** ABU 14.60 hrs (2.74 + 6.11 + 5.76), BANU 3.24 hrs (2.05 + 0.74 + 0.45) | #** ABU 14.60 hrs (2.74 + 6.11 + 5.76), BANU 3.24 hrs (2.05 + 0.74 + 0.45) | ||
− | #** Total triggers collected: | + | #** Total triggers collected: 1648 M |
+ | #** The first of 2 parasitic TRD runs has been taken. | ||
+ | #** Sascha made preparations fro trigger studies but postponed the actual studies until Sunday | ||
+ | #** Once, the goniometer got stuck, and Hovanes had to fix it [https://logbooks.jlab.org/entry/3459894] | ||
#* RootSpy issues: | #* RootSpy issues: | ||
#** "Reset" does not reset all histograms [https://logbooks.jlab.org/entry/3459921] [https://logbooks.jlab.org/entry/3459926] - Fixed by David - Still broken? [https://logbooks.jlab.org/entry/3459989] | #** "Reset" does not reset all histograms [https://logbooks.jlab.org/entry/3459921] [https://logbooks.jlab.org/entry/3459926] - Fixed by David - Still broken? [https://logbooks.jlab.org/entry/3459989] | ||
− | #** No reset of normalization for pi0 plot at "reset" [https://logbooks.jlab.org/entry/3459948] -Fixed by David | + | #** No reset of normalization for pi0 plot at "reset" [https://logbooks.jlab.org/entry/3459948] - Fixed by David |
− | #** Run number on the HDMONITOR elog plots is | + | #** Run number on the HDMONITOR elog plots [https://logbooks.jlab.org/book/hdmonitor] is stuck at 30653 [https://logbooks.jlab.org/entry/3460032] |
#* DAQ issues: | #* DAQ issues: | ||
− | #** Zero counting rate for some ROCs [https://logbooks.jlab.org/entry/3460034] | + | #** Zero counting rate for some ROCs [https://logbooks.jlab.org/entry/3460034] while occupancy plots are normal |
# Monitoring | # Monitoring | ||
− | #* | + | #* New PSC reference plot [https://logbooks.jlab.org/entry/3459853] [https://logbooks.jlab.org/entry/3460014] |
− | + | ||
#* New FDC reference plot [https://logbooks.jlab.org/entry/3460009] | #* New FDC reference plot [https://logbooks.jlab.org/entry/3460009] | ||
#* New holes in FCAL occupancy [https://logbooks.jlab.org/entry/3460016] | #* New holes in FCAL occupancy [https://logbooks.jlab.org/entry/3460016] |
Revision as of 10:09, 19 February 2017
<- Back to Run Coordination Meetings: Spring 2017 Run
Contents
Sunday, February 19
- Accelerator Status
- Hall-D/GlueX items
- In the last 24 hours:
- ABU 14.60 hrs (2.74 + 6.11 + 5.76), BANU 3.24 hrs (2.05 + 0.74 + 0.45)
- Total triggers collected: 1648 M
- The first of 2 parasitic TRD runs has been taken.
- Sascha made preparations fro trigger studies but postponed the actual studies until Sunday
- Once, the goniometer got stuck, and Hovanes had to fix it [5]
- RootSpy issues:
- DAQ issues:
- Zero counting rate for some ROCs [12] while occupancy plots are normal
- In the last 24 hours:
- Monitoring
- New PSC reference plot [13] [14]
- New FDC reference plot [15]
- New holes in FCAL occupancy [16]
- Low level monitoring report
- Run Plan
- Production, production, production...
- Sascha's trigger studies (2-3 hrs)
- Parasitic TRD run (~30 min)
- Offline Analysis?
- Any Other Business?
Saturday, February 18
- Accelerator Status
- Beam was mostly stable in the last 24 hrs [17]
- BPM calibration
- Hall-D/GlueX items
- In the last 24 hours:
- ABU 16.73 hrs (5.80 + 5.32 + 5.61), BANU 1.73 hrs (0.28 + 0.72 + 0.73)
- Total triggers collected: 1813 M
- Better settings for JTV 7 Nitrogen supply valve
- Oscillating target pressure? [23]
- Progress on fixing random 32ns shift of TDC times [24]
- Software issues:
- In the last 24 hours:
- Monitoring
- Run Plan
- Production, production, production...
- Harp scan
- Sascha's trigger studies?
- Offline Analysis?
- Beam energy so far
very stable around 11.650 GeV - Preliminary flux estimate
From 1.0*107 to 1.2*107 for different diamond orientations at 100nA
- Beam energy so far
- Any Other Business?
Friday, February 17
- Accelerator Status
- Hall was in controlled access from 7:00 till 16:30 for RF separator studies
- Work on TRD GEM by Kondo during this time
- Alexandre has retrieved supplemental dosimetry from the tagger
- Production restarted at 17:30
- Stable beam since then (max 10 minutes off on 2 occasions) [30]
- Radiation levels are about the same as earlier [31]
- Harp scans: MCC and ours.
- In terms of (Sigma_X, Sigma_Y) at 5C11, 5C11B and radiator:
- (0.83, 0.32), (0.63, 0.24), (0.68, ??? - the fit has failed)
- Beam is ~20% tighter in X and twice narrower in Y comparing with a day ago
- Photon transmission is about the same as a day ago
- In terms of (Sigma_X, Sigma_Y) at 5C11, 5C11B and radiator:
- BPM calibration?
- AD00 BPM is no longer the same as AD00C BCM but only 40% of it [32]
- Hall was in controlled access from 7:00 till 16:30 for RF separator studies
- Hall-D/GlueX items
- In the last 24 hours:
- ABU 10.32 hrs (0 + 4.54 + 5.78), BANU 2.13 hrs (0 + 1.17 + 0.96)
- Total triggers collected: 1046 M
- The usual DAQ and RootSpy issues make shifts entertaining
- In the last 24 hours:
- Monitoring
- 32ns TDC-ADC offsets:
- Low Level Monitoring Report (today)
- Low Level Monitoring Report (Feb 16)
- Run Plan
- Production, production, production...
- Sascha's trigger studies?
- Offline Analysis?
- Any Other Business?
Thursday, February 16
- Accelerator Status
- Stable accelerator running over the last 24 hours
- Harp scans:
- MCC scans before and after Todd's script
"Good enough -- horizontal convergence is nearly spot on, and vertical convergence is a little shallow but ok." - Our scan: before and after Todd's script
- In terms of (Sigma_X, Sigma_Y) at 5C11, 5C11B and radiator:
- Before: (1.31, 0.63), (1.08, 0.73), (1.03, 0.41)
- After : (1.07, 0.51), (0.79, 0.50), (0.78, 0.32)
- MCC scans before and after Todd's script
- Convergence studies from Hovanes: Feb 15 vs Feb 9
- Beam sigma at the radiator: 0.6cm (Feb 15) vs 0.5cm (Feb 9)
"... uncertainties ... a lot larger compared to Feb 9. It is hard to make any conclusions about the improvement of the spot."
- Beam sigma at the radiator: 0.6cm (Feb 15) vs 0.5cm (Feb 9)
- Work on RF separation will start at 7:30 AM today and last for 2-3 hours
- Hall-D/GlueX items
- In the last 24 hours:
- ABU 17.66 hrs (4.97 + 6.37 + 6.32), BANU 2.21 hrs (1.27 + 0.40 + 0.54)
- Total triggers collected: 1856 M
- A usual assortment of DAQ crashes
- RootSpy tips:
- Restarting cMsg server
- Multiple instances of RootSpy on gluon47
"... no more than 1 or 2 instances running in the counting house at any point in time."
- New BCAL gain constants in ccdb [35]
- In the last 24 hours:
- Monitoring
- A new instance of 32ns ADC-TDC offset: [36]
- Run Plan
- 7:00 AM - 7:30 AM ==> Hall safety walk-through (After RADCON does it job)
- 7:30 AM - about 10 AM ==> MCC works on RF separation
- A new harp scan after RF separation work is done
- Production data
- Offline Analysis?
- Any Other Business?