Difference between revisions of "Run Planning Meeting Notes, May 2-May 6, 2018"
From GlueXWiki
(→Friday, May 4 at 08:45) |
(→Friday, May 4 at 08:45) |
||
Line 10: | Line 10: | ||
#* Network problems on accelerator site, CHL1 trip, RF recovery, Hall A pass change | #* Network problems on accelerator site, CHL1 trip, RF recovery, Hall A pass change | ||
#* CW beam back at 9pm | #* CW beam back at 9pm | ||
− | #* Harp Scan | + | #* Harp Scan [https://logbooks.jlab.org/entry/3571611], [https://logbooks.jlab.org/entry/3571616], [https://logbooks.jlab.org/entry/3571631], [https://logbooks.jlab.org/entry/3571632], [https://logbooks.jlab.org/entry/3571634] |
#* Raw mode run | #* Raw mode run | ||
#* Production running | #* Production running | ||
#Issues: | #Issues: | ||
# Reports: | # Reports: | ||
+ | #* Effect of W-foil on CDC hit multiplicity [https://logbooks.jlab.org/entry/3571349] | ||
#* ω yields w/o W foil [https://logbooks.jlab.org/entry/3571417] | #* ω yields w/o W foil [https://logbooks.jlab.org/entry/3571417] | ||
# Run Plan | # Run Plan |
Revision as of 22:27, 3 May 2018
<- Back to Run Coordination Meetings:Fall2017 Spring2018 Run
Friday, May 4 at 08:45
- Notes from the previous 24 hours:
- Issues:
- Reports:
- Run Plan
- Friday
- Fast raster scan (9am, 60min)
- TAC run (10am, 1 shift)
- Saturday
- Production
- Sunday
- 5am end of physics, 6am end of run, restricted access from 10am
- Week 17
- Friday