Difference between revisions of "May 24, 2018 DIRC Optical Box"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
Line 30: | Line 30: | ||
#* [https://halldweb.jlab.org/doc-private/DocDB/ShowDocument?docid=3576 Module orientation and LV/HV controls] | #* [https://halldweb.jlab.org/doc-private/DocDB/ShowDocument?docid=3576 Module orientation and LV/HV controls] | ||
#* Water skid and nitrogen system | #* Water skid and nitrogen system | ||
− | #* Interlocks | + | #* Interlocks |
# Discussion of assembly procedure and timeline: | # Discussion of assembly procedure and timeline: | ||
#* [https://halldweb.jlab.org/wiki/images/a/aa/20180220_GlueX_Assembly_Sequence.pdf Plans for assembly and testing at Bates and in Hall D] | #* [https://halldweb.jlab.org/wiki/images/a/aa/20180220_GlueX_Assembly_Sequence.pdf Plans for assembly and testing at Bates and in Hall D] |
Revision as of 09:04, 24 May 2018
Meeting Information
GlueX DIRC Optical Box Meeting
Thursday May 24, 2018
10:00 am, EDT
JLab L207
Connection Using Bluejeans
- To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 846453895.
- To join via a Web Browser, go to the page [1] https://bluejeans.com/846453895 .
- To join via phone, use one of the following numbers and the Conference ID: 846453895
- US or Canada: +1 408 740 7256 or
- US or Canada: +1 888 240 2560
- More information on connecting to bluejeans is available.
Agenda
- Announcement
- Optical box status
- Status update (Ernie and Jason)
- Box production at Lesker: plan for visit and delivery estimate
- PMT test fixture: Assembly procedure and discussion
- Window quotes and delivery schedule
- Dark box conceptual design
- Other items and quotes
- Status update (Ernie and Jason)
- Installation of bar boxes and optical box in Hall D
- Discussion of installation schedule in Hall D (Tim, et al)
- Controls discussion (All)
- Module orientation and LV/HV controls
- Water skid and nitrogen system
- Interlocks
- Discussion of assembly procedure and timeline:
- AOB