Difference between revisions of "July 19, 2018 DIRC Optical Box"
From GlueXWiki
(Created page with "== Meeting Information == GlueX DIRC Optical Box Meeting<br> Thursday July 19, 2018<br> 10:00 am, EST<br> JLab A110 <br> == Connection Using Bluejeans == # To join via Polyc...") |
(→Agenda) |
||
Line 29: | Line 29: | ||
#* [[Media:DIRC_INSTALL_SCHEDULEv2.pdf|Current "optimistic" schedule]]: optical box delivery July 14 | #* [[Media:DIRC_INSTALL_SCHEDULEv2.pdf|Current "optimistic" schedule]]: optical box delivery July 14 | ||
#* Contingency: [[Media:Oct OB delivery.pdf|Latest possible installation schedule]]: optical box delivery October 10 | #* Contingency: [[Media:Oct OB delivery.pdf|Latest possible installation schedule]]: optical box delivery October 10 | ||
+ | #* Requirements for mechanical install of optical box: delivery required by August 12 | ||
# Mirror box laser alignment | # Mirror box laser alignment | ||
#* Update on geometry and laser projections (Bill) | #* Update on geometry and laser projections (Bill) |
Revision as of 18:22, 18 July 2018
Meeting Information
GlueX DIRC Optical Box Meeting
Thursday July 19, 2018
10:00 am, EST
JLab A110
Connection Using Bluejeans
- To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 846453895.
- To join via a Web Browser, go to the page [1] https://bluejeans.com/846453895 .
- To join via phone, use one of the following numbers and the Conference ID: 846453895
- US or Canada: +1 408 740 7256 or
- US or Canada: +1 888 240 2560
- More information on connecting to bluejeans is available.
Agenda
- Announcement
- Optical box status
- Fabrication status update (Ernie and Jason)
- Box production at Lesker
- Mirror strong back delivery and assembly
- Mirror cutting
- Window procurement
- Assembly sequence and testing plans at Bates
- Dark box enclosure development: air flow calculations
- DIRC BBox Split Flange Seal (Jim/Tim)
- Fabrication status update (Ernie and Jason)
- Installation schedule discussion:
- Current "optimistic" schedule: optical box delivery July 14
- Contingency: Latest possible installation schedule: optical box delivery October 10
- Requirements for mechanical install of optical box: delivery required by August 12
- Mirror box laser alignment
- Update on geometry and laser projections (Bill)
- Optical Box Alignment strawman (Tim)
- Laser Alignment fixture (Tim)
- AOB