Difference between revisions of "Run Planning Meeting Notes, Sep 28-Oct 3, 2018"
From GlueXWiki
(→Friday, Sep 28 at 08:45) |
(→Friday, Sep 28 at 08:45) |
||
Line 8: | Line 8: | ||
== Friday, Sep 28 at 08:45 == | == Friday, Sep 28 at 08:45 == | ||
# Notes from the previous 24 hours: | # Notes from the previous 24 hours: | ||
+ | #*Beam position erratic throughout the day & first half of swing [https://logbooks.jlab.org/entry/3599221 day] [https://logbooks.jlab.org/entry/3598591 swing] | ||
+ | #*Energy drift [https://logbooks.jlab.org/entry/3599126 pathlength corrected] | ||
+ | #*Sergey completed first set of DAQ tests | ||
+ | #*Stabilized mid-swing enough to attempt alignment but spot is huge 1.2 x 1.5mm | ||
+ | #*Collected 'production' data overnight, concerned about quality [https://logbooks.jlab.org/entry/3599614 cobrems gui] | ||
#CEBAF: | #CEBAF: | ||
− | |||
− | |||
#Action Items: | #Action Items: | ||
+ | #* Update reference plots | ||
#Issues: | #Issues: | ||
+ | #* Network problems | ||
# Reports: | # Reports: | ||
#*Monitoring | #*Monitoring | ||
# Run Plan: [https://halldweb.jlab.org/wiki/images/a/a7/Fall18_week2.jpg Run plan] | # Run Plan: [https://halldweb.jlab.org/wiki/images/a/a7/Fall18_week2.jpg Run plan] | ||
+ | #* Beam off at 9 for pass change | ||
+ | #* Sasha PS and Richard TAGM threshold not done yet | ||
#*Coordinate with C for TAC run - on or after Wed (otherwise need access), plan to install converter on Tuesday | #*Coordinate with C for TAC run - on or after Wed (otherwise need access), plan to install converter on Tuesday | ||
#*[http://accboard.acc.jlab.org/ Acc whiteboard] | #*[http://accboard.acc.jlab.org/ Acc whiteboard] | ||
#*[https://halldweb.jlab.org/online/whiteboard/ Counting house whiteboard] | #*[https://halldweb.jlab.org/online/whiteboard/ Counting house whiteboard] | ||
# AOB | # AOB |
Revision as of 07:09, 28 September 2018
<- Back to Run Coordination Meetings:Fall2018 Run
Friday, Sep 28 at 08:45
- Notes from the previous 24 hours:
- Beam position erratic throughout the day & first half of swing day swing
- Energy drift pathlength corrected
- Sergey completed first set of DAQ tests
- Stabilized mid-swing enough to attempt alignment but spot is huge 1.2 x 1.5mm
- Collected 'production' data overnight, concerned about quality cobrems gui
- CEBAF:
- Action Items:
- Update reference plots
- Issues:
- Network problems
- Reports:
- Monitoring
- Run Plan: Run plan
- Beam off at 9 for pass change
- Sasha PS and Richard TAGM threshold not done yet
- Coordinate with C for TAC run - on or after Wed (otherwise need access), plan to install converter on Tuesday
- Acc whiteboard
- Counting house whiteboard
- AOB