Difference between revisions of "October 8, 2018 DIRC"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
Line 32: | Line 32: | ||
# Software/simulations | # Software/simulations | ||
#* Finalizing DIRC "as-built" geometry: support frames, bar box internals, etc. (Yunjie) | #* Finalizing DIRC "as-built" geometry: support frames, bar box internals, etc. (Yunjie) | ||
− | #* LED generator (Yunjie) | + | #* LED generator ([https://halldweb.jlab.org/wiki/images/4/41/LED_100818.pdf Yunjie]) |
#* Time-based studies (Maria) | #* Time-based studies (Maria) | ||
#* Software [https://halldweb.jlab.org/wiki/index.php/DIRC_Software_Overview overview] and [https://halldweb.jlab.org/wiki/index.php/DIRC_Software_Tasks tasks] (All) | #* Software [https://halldweb.jlab.org/wiki/index.php/DIRC_Software_Overview overview] and [https://halldweb.jlab.org/wiki/index.php/DIRC_Software_Tasks tasks] (All) |
Revision as of 12:16, 8 October 2018
Meeting Information
GlueX DIRC Meeting
Monday October 8, 2018
1:00 pm, EDT
JLab room A110
Connection Using Bluejeans
- To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 846453895.
- To join via a Web Browser, go to the page [1] https://bluejeans.com/846453895 .
- To join via phone, use one of the following numbers and the Conference ID: 846453895
- US or Canada: +1 408 740 7256 or
- US or Canada: +1 888 240 2560
- More information on connecting to bluejeans is available.
Agenda
- Announcements
- JLab management still deciding how to make up lost time this Fall
- Preliminary plan from Hall D at CM: CompCal is priority for Fall, but continue with DIRC installation in parallel
- Optical box
- Fabrication status update (Ernie and Jason)
- Mirror boxes delivered to JLab! (Ernie)
- Warping of window flange and plan to address at Lesker (Ernie/Tim)
- Dark box enclosure (Jason)
- Quartz window (with modified flange) (Ernie)
- Testing in ESB
- Mirror box laser alignment (Bill)
- Installation schedule: [2]
- Fabrication status update (Ernie and Jason)
- DAQ integration
- Slow controls
- Software/simulations
- Addressing ERR review recommendations
- Recommendations pertaining to Fall 2018 DIRC commissioning should be addressed before October installation (required for new beam time request)