Difference between revisions of "Run Planning Meeting Notes, Nov 1-Nov 8, 2018"
From GlueXWiki
Line 13: | Line 13: | ||
##Rest of time - production | ##Rest of time - production | ||
# Issues | # Issues | ||
− | ##Check with Elton re BCAL N/S | + | #*[https://logbooks.jlab.org/entry/3618692 Shift checklist Qs, from Mark] |
+ | #*Check with Elton re BCAL N/S | ||
# Reports | # Reports | ||
+ | #*[https://logbooks.jlab.org/entry/3618696 CDC background analysis, from Sergey] | ||
#*[https://docs.google.com/spreadsheets/d/1NffTc4-S5PbTMSuH_pp7ZYsGRH4JC_WSVo770_iJYt0/edit#gid=1865737386 Trigger Spreadsheet] | #*[https://docs.google.com/spreadsheets/d/1NffTc4-S5PbTMSuH_pp7ZYsGRH4JC_WSVo770_iJYt0/edit#gid=1865737386 Trigger Spreadsheet] | ||
# Plans | # Plans |
Revision as of 20:54, 31 October 2018
<- Back to Run Coordination Meetings:Fall2018 Run
- Trigger Spreadsheet Started Filling out on 9/28/18
- Run Plan Google Calendar
- Accel. Plan Google Calendar
Thursday, Nov 1 at 08:45
- Last 24h
- 7GeV test run completed
- Raw mode run completed
- Rest of time - production
- Issues
- Shift checklist Qs, from Mark
- Check with Elton re BCAL N/S
- Reports
- Plans
- AOB