Difference between revisions of "Run Planning Meeting Notes, Feb. 14-Fev 21, 2019"
From GlueXWiki
(→Thursday, Feb. 14 at 08:45) |
(→Thursday, Feb. 14 at 08:45) |
||
Line 4: | Line 4: | ||
#** Beam profile and convergence by Jay:https://logbooks.jlab.org/entry/3652506 | #** Beam profile and convergence by Jay:https://logbooks.jlab.org/entry/3652506 | ||
#* DIRC data taking. | #* DIRC data taking. | ||
+ | #*# DIRC analysis is on-going. | ||
# Issues | # Issues | ||
#* Cryo Water Temperature jump to 72F (limit 70F). | #* Cryo Water Temperature jump to 72F (limit 70F). |
Revision as of 09:44, 14 February 2019
Thursday, Feb. 14 at 08:45
- Past 24 hours:
- Acceptable quality beam established early morning around 11:00 am.
- Beam profile and convergence by Jay:https://logbooks.jlab.org/entry/3652506
- DIRC data taking.
- DIRC analysis is on-going.
- Acceptable quality beam established early morning around 11:00 am.
- Issues
- Cryo Water Temperature jump to 72F (limit 70F).
- Due to pump switch: https://logbooks.jlab.org/entry/3652512
- IOC lost communication
- IOCHDCOL failed at 21:30. Reported to us by MCC at 0:00. Reset at 1:50 am. Hovanes verified things are ok at 3am. https://logbooks.jlab.org/entry/3652920
- DIRC SSP problem:
- DAQ stopped twice due to the out of sync issue.
- Tagger RF time: https://logbooks.jlab.org/entry/3652533
- hdview2 is work working
- Cryo Water Temperature jump to 72F (limit 70F).
- Today:
- No planned access
- Opportunistic access requested by Kenoe to work on GEM.
- DIRC nominal running (MOROC threshold scan?)