Difference between revisions of "Run Planning Meeting Notes, Feb 28 - Mar 6, 2019"
From GlueXWiki
(→Thursday, Feb. 28 at 08:45) |
|||
Line 5: | Line 5: | ||
* [https://halldweb.jlab.org/wiki/index.php/Spring_2019_Primex PrimEx-η run plan] | * [https://halldweb.jlab.org/wiki/index.php/Spring_2019_Primex PrimEx-η run plan] | ||
* To join via a Web Browser, go to the page [https://bluejeans.com/660743227 https://bluejeans.com/660743227] | * To join via a Web Browser, go to the page [https://bluejeans.com/660743227 https://bluejeans.com/660743227] | ||
+ | |||
== Thursday, Feb. 28 at 08:45 == | == Thursday, Feb. 28 at 08:45 == | ||
Line 13: | Line 14: | ||
# Today: | # Today: | ||
#* Remove Be target @ 8 AM, lockup Hall by noon? | #* Remove Be target @ 8 AM, lockup Hall by noon? | ||
− | #* | + | #** Will cylindrical Be holder cell be removed? |
+ | #* Production running without target until Friday morning? | ||
# Tomorrow: | # Tomorrow: | ||
− | #* LHe target | + | #* LHe target installation: |
− | #** | + | #** Hall open at 6 am for bleeding up beamline |
− | #** Other work in the Hall? | + | #** Other work in the Hall? Start counter installation? |
+ | # LHe target cooldown and filling | ||
+ | #* When and how much empty LHe target data do we want? | ||
+ | #* Chris expects ~10-12 hours required for cooldown. He would like to be here during the initial fill. | ||
+ | #** Fill target over the weekend or wait until Monday? |
Revision as of 18:00, 27 February 2019
Contents
- Run_Coordination_Meetings:Spring2019_Run
- PrimEx-η run plan
- To join via a Web Browser, go to the page https://bluejeans.com/660743227
Thursday, Feb. 28 at 08:45
- Past 24 hours:
- Compton Production: ??? M triggers with Be
- Issues:
- FYI: Beam orbit locks off
- Today:
- Remove Be target @ 8 AM, lockup Hall by noon?
- Will cylindrical Be holder cell be removed?
- Production running without target until Friday morning?
- Remove Be target @ 8 AM, lockup Hall by noon?
- Tomorrow:
- LHe target installation:
- Hall open at 6 am for bleeding up beamline
- Other work in the Hall? Start counter installation?
- LHe target installation:
- LHe target cooldown and filling
- When and how much empty LHe target data do we want?
- Chris expects ~10-12 hours required for cooldown. He would like to be here during the initial fill.
- Fill target over the weekend or wait until Monday?