Run Planning Meeting Notes, November 4 - November 10, 2021
From GlueXWiki
MCC whiteboard Meeting Bluejeans 660743227 Trigger Counter
Thursday November 04
- Last 24h:
- Maintenance day
- Replaced FCAL 15 bases [1]
- Restored beam at X:XXpm
- Harp scan
- Recorded XXXM+ events with full LHe4 target
- Issues:
- Plan:
- Continue production at 200nA with the solenoid on after that.
- MCC (Jay) discussed possibility to move up the energy shift to Thu, swing
- Controlled access planned for maintenance work (e.g. FCAL [2])
- Beam energy change planned for 11/05-11/07
- RadCon survey for Friday morning is requested
- Safety Walkthrough scheduled for Friday 2pm
- EEL Closure from November 5th, 6pm to November 8th, 6am and November 12th, 6pm to November 15th, 6am