April 22, 2022 Tech group SAD meeting
From GlueXWiki
Meeting Time and Place =
Friday April 22 2022 10:30am Hall D Counting House and Teams
Agenda
- Safety - poly tank fell off truck
- Work location status
- Accelerator schedule - HCO starts soon
- Hall D SAD Tasks
- CPP INstall O:\halld_engineering\Installation Schedules
- Microscope move/Hodoscope - poly shielding complete
- Moveable Lead absorber - Tim to Write procedure
- Target - Bobby - fit check - need drawings
- Gas - Scot
- Helium bag
- PS Parasitic Detectors stages
- FCAL Insert Module fabrication
- 40 brass straps per week needed
- matching mu metal to steel shields
- cutting tool
- Tagger NMR repair - Scot
- Tagger controls UPS
- BCAL Coldshot Chiller commissioning - Josh
- Target/Goni Turbo repair - Keith
- TEDF move in May to EEL stockroom area
- CPP INstall O:\halld_engineering\Installation Schedules
- JT file creation - Anthony gave presentation - file and instructions on O drive
- FCAL Insert Drawings
- New Profiler install
- New 3x3 CCAL for TAC Media:CPP_TAC.pdf
- Tagger Radiator Mod Media:Fork_mod.pdf
- Controls
- Solenoid vacuum controls
- General Maintenance
- On Call - Josh
- ePAS Training and trial https://www.jlab.org/esh/epas
Action Items
- Prepare for HCO
- Set up next PS parasitic meeting