Hall-B Schedule
From GlueXWiki
All travel, shipping and task schedule information, in connection to the BCAL beam tests at Hall-B (Sep. 2006), is kept on this page.
- Tentative dates for Regina personnel: Rafael (Aug. 19 - Oct. 3), Blake (Aug 19. - Oct. 3), Kathryn (Aug. 19 - Aug. 26), Zisis (Aug. 19 - Aug. 26, Sep. 19 - Oct. 1), Ioanna (Sep. 19 - Oct. 1), George (Sep. 22 - Oct. 1), Garth (Sep. 22 - Oct. 1)
- Tentative dates for IU personnel: Eric (Aug. 20 - Aug.27)
- Earliest occupancy: August 16, targeted occupancy: August 22.
- Installation_Procedures: craning (1 day), bolting (1 day), survey (1 day), PMT mounting (1 day), cosmics (1-2 weeks)
- Tentative dates for IU BCAL Cart Shipment: Ship Aug. 17-18 for arrival on Aug. 21
- Tentative dates for Regina Module Shipment: Ship Aug. 13-14 for arrival on Aug. 21
The Table below shows the GlueX-related items from the most recent Hall-B schedule.
ID | Task Name | Work | Duration | Start | Finish | % Work Complete |
---|---|---|---|---|---|---|
151 | GlueX calorimeter | 196 hrs | 9.5 days | Thu 8/3/06 | Wed 8/16/06 | 0% |
152 | Install calorimeter stand | 72 hrs | 3 days | Thu 8/3/06 | Mon 8/7/06 | 0% |
3 | Doug | 24 hrs | Thu 8/3/06 | Mon 8/7/06 | 0% | |
4 | Calvin | 24 hrs | Thu 8/3/06 | Mon 8/7/06 | 0% | |
10 | Crane | 24 hrs | Thu 8/3/06 | Mon 8/7/06 | 0% | |
153 | Install Bcal support | 0 hrs | 1 day | Tue 8/8/06 | Tue 8/8/06 | 0% |
154 | Install calorimeter | 120 hrs | 5 days | Wed 8/9/06 | Tue 8/15/06 | 0% |
3 | Doug | 40 hrs | Wed 8/9/06 | Tue 8/15/06 | 0% | |
4 | Calvin | 40 hrs | Wed 8/9/06 | Tue 8/15/06 | 0% | |
10 | Crane | 40 hrs | Wed 8/9/06 | Tue 8/15/06 | 0% | |
155 | Install Down Stream Helium Bag | 4 hrs | 4 hrs | Wed 8/16/06 | Wed 8/16/06 | 0% |
2 | Steve | 4 hrs | Wed 8/16/06 | Wed 8/16/06 | 0% | |
156 | SURVEY | 44 hrs | 15.63 days | Thu 7/27/06 | Thu 8/17/06 | 0% |
157 | Survey Frascati magnets | 8 hrs | 8 hrs | Tue 8/8/06 | Tue 8/8/06 | 0% |
12 | Survey | 8 hrs | Tue 8/8/06 | Tue 8/8/06 | 0% | |
158 | Survey Pair Spectrometer | 8 hrs | 1 day | Wed 8/9/06 | Wed 8/9/06 | 0% |
12 | Survey | 8 hrs | Wed 8/9/06 | Wed 8/9/06 | 0% | |
159 | Survey GlueX calorimeter | 8 hrs | 1 day | Wed 8/16/06 | Thu 8/17/06 | 0% |
12 | Survey | 8 hrs | Wed 8/16/06 | Thu 8/17/06 | 0% | |
160 | Survey Target | 8 hrs | 1 day | Thu 7/27/06 | Fri 7/28/06 | 0% |
12 | Survey | 8 hrs | Thu 7/27/06 | Fri 7/28/06 | 0% |