GlueX TOF Meeting, August 30, 2012
GlueX TOF Meeting
Thursday, August 30, 2012
10:00 am EDT
JLab: CEBAF Center, F326
Agenda
- Announcements
- Review of last TOF bi-weekly meeting
- Mechanical design
- Prototype status
- TDC Purchase
- Contract Status
- Calibration and Alignment
- Technical Design Report contribution
Communication
Videoconference
- ESNet: 8542553
- EVO: EVO site
- meeting link
- Phone bridge ID: 13 7104
Slides
Talks can be deposited in the directory /group/halld/www/halldweb1/html/talks/2012-3Q
on the JLab CUE. This directory is accessible from the web at https://halldweb1.jlab.org/talks/2012-3Q/ .
Minutes
TOF meeting notes, Aug. 30
ian, sasha, randall, paul tim, mark, beni, fernando
last time short discussion of items purchased update of mini-tof discussion of changing materials due to length and weight send out calibration document
TDCs have been ordered signal distribution issues need to be planned, additional modules need to be built by us hall b has prototypes, sergey thinks they will need a new design
gaining experience with flash ADC's FSU has VME 64x crate, pin removed for serial connector must use internal clock or provide external clock fernando will look and see what is available production units will go to UMass in a month late oct, modules via umass should arrive
mini-tof update
Randall
package of bent plates arrived, some may not work not stainless making light guides long versions made for first time pmt sleeves completed shield holders completed all light guides manufactured more material requested
paul and ian will meet on glueing fixture for 5 paddles at once box of plates delivered to old central receiving