Fall 2016 Run time charts
From GlueXWiki
Revision as of 14:40, 3 November 2016 by Deurpam (Talk | contribs) (→Runplan time charts (goniometer available from the start))
Runplan time charts (goniometer available from the start)
Commissioning time chart:Commissioning time chart. Week 1. Time t=0 corresponds to 11/14/2016. The horizontal scale is the time during which beam is available (in other word, it would be the real time with 100% of beam efficiency). The task time estimates given on the plot have 100% contingency.
Commissioning time chart. Week 2.
Commissioning time chart. Week 3.
Commissioning time chart. Week 4.
Commissioning time chart. Week 5.
Commissioning time chart. Week 6.