Run Planning Meeting Notes, Feb 12-Feb 28, 2018
From GlueXWiki
<- Back to Run Coordination Meetings:Fall2017 Spring2018 Run
Contents
Thursday, February 22
- Notes from the previous 24 hours:
- Continued production data until 1:30pm
- Secretary Perry toured Hall D
- Beam delivery shaky: Swing shift summary
- DAQ/cMesg/rootSPY issues
- Dipole trip
- Transmission looks ok
- Production data
- Issues:
- Harp scan EPICS screenshot
- FDC trips: issue on 1 channel; Beni lowered the bias.
- Large Y-oscillations in 511C
- Photon beam intensity anomaly
- Reports (?):
- Today's run plan Run Plan Google Calendar Accel. Run Plan Google Calendar:
- Harp scan once beam returns
- Production data
Friday, February 23
- Notes from the previous 24 hours:
- Production data
- Beam taken away 11:15-14:14 for linac issues
- Owl Shift Summary: rho, omega, phi triggers
- Energy nudging - 5 times in last 24 hours
- Issues:
- ADC in slot 16 of the TOF crate is still commented out in the config file
- FDC TDC-ADC timing shifts
- Are these issues?: Problem starting run, ROCSTPSC2 and ROCTAGM2 have no events, Power cycle the ROCTRIG2 and Start the DAQ again, ROCFCAL3
- Reports (?):
[* https://logbooks.jlab.org/entry/3536973 Low level monitoring report]
- Multi-scale active collimator calibration any followup?
- Planning:
- Today's run plan Run Plan Google Calendar Accel. Run Plan Google Calendar:
- Harp scan at 7am
- Production data
- Current timings, CDC and FDC timings
- CDC delay reduced im FCAL_BCAL_PS_m9.conf for just one diamond run and then restore.
Saturday, February 24
- Notes from the previous 24 hours:
Sunday, February 25
- Notes from the previous 24 hours:
Monday, February 26
- Notes from the previous 24 hours:
Tuesday, February 27
- Notes from the previous 24 hours:
Thursday, February 28
- Notes from the previous 24 hours: