Run Planning Meeting Notes, Feb. 14-Fev 21, 2019
From GlueXWiki
Thursday, Feb. 14 at 08:45
- Past 24 hours:
- Acceptable quality beam established early morning around 11:00 am.
- Beam profile and convergence by Jay:https://logbooks.jlab.org/entry/3652506
- DIRC data taking.
- Acceptable quality beam established early morning around 11:00 am.
- Issues
- Cryo Water Temperature jump to 72F (limit 70F).
- Due to pump switch: https://logbooks.jlab.org/entry/3652512
- IOC lost communication
- IOCHDCOL failed at 21:30. Reported to us by MCC at 0:00. Reset at 1:50 am. Hovanes verified things are ok at 3am. https://logbooks.jlab.org/entry/3652920
- DIRC SSP problem:
- DAQ stopped twice due to the out of sync issue.
- Tagger RF time:
- Cryo Water Temperature jump to 72F (limit 70F).