Coil Test Weekly Meeting 25-Nov-2009
From GlueXWiki
Solenoid Coil Test Weekly Meeting
Location and Time
- Wed 25-Nov-2009 9:45 am ARC 428
Agenda
- QWeak area: when can we get in, how will we use it - Tom
- Ordering cryo can - George
- Cryo and electrical interface, relief system - Josh, George
- Cryogenic wire and wire insulation - Scot, George
- Coil 1 testing and wire replacement - George
- Coil 2 cost/schedule review, etc. - George
- Coil 3 statement of work, visit and IUCF contract - George, Tom
- Coil 4 controls wiring replacement - George
- P&I, controls drawings, narrative - George, Mark S, Mark W
- Construction/installation sequence drawings - George, Chuck
- Ordering platform - George
- Shipping jack stands and rails from IUCF - Tom
- PLC programming and testing - Mark W
- we have approximately one man-week of Steve Lassiter's time
- how to use it wisely?
- Ordering remaining controls instrumentation and components - Scot
- Controls racks in F117: when do we begin installation of controls instrumentation - Mark S, Scot
- FastTrack update strategy - George
- Review "Top To-Do" items - Elliott
- Review of recent progress, identify action items - All