This will be a short meeting due to the JLab Run-A-Round
Agenda
- Announcements
- Collaboration Meeting Schedule
- Review of minutes from 8-May-2013 meeting
- Build and release system - Elliott
- Status of DAQ testing in Rack Room - Dave A, Bryan
- Counting House update - Hovanes, Elliott
- Solenoid test update - Elliott
May not get to these
- EPICS update - Hovanes
- Controls update - Elliott, Hovanes
- JInventory database - Elliott
- DAQ group projects- Bryan, Dave A, Graham, Carl, Vardan, Elliott
- EVIO, cMsg, CODA3, ECS/CSS, disentangler, readout list, Java/cMsg GUI
- Electronics, trigger and DAQ status reports - Chris, Alex, Dave, Fernando, Ben, Ed, William, Bryan
- Mantis Task Tracker
- Midas Elog
- Upcoming topics
- Calibration/Alignment issues?
- Status of processing uncompressed and compressed simulated raw data and monitoring/L3 farm - Dave L, Elliott
- What online projects can other groups take over? - Elliott
- Status and schedule of Hall D projects proposed to be done by DAQ group - Graham
- Linux SBC configuration, installation, booting - by Bryan
- InfiniBand hardware specification, purchase, installation - by Dave A
- Farm manager CODA component - by Vardan
- Ed to talk more on FPGA programming
Time/Location
1:30 PM Wed 22-May-2013 CC A110
Announcements
Next Meeting
No meeting in two weeks due to collaboration meeting
1:30 PM Wed 19-Jun-2013 CC F326