GlueX Calibration Meeting
Wednesday, September 9, 2015
11:00 am, EDT
JLab: TED 2561B
Communication Information
Remote Connection
You can connect using BlueJeans using the meeting number 630 804 895 . (Click "Expand" to the right for more details -->):
- Make sure you have created a BlueJeans account via your JLab CUE account using this link:
- http://jlab.bluejeans.com (You should only need to do this once)
- Meeting ID: 630804895
- (you may need to type this in, depending how you connect)
- If connecting via Web Browser: click this link (no passcode is needed):
- If connecting via iOS or Android App:
- Use your JLab e-mail address to log in and then enter the meeting ID given above to join the meeting
- If connecting via Phone: Dial one of the following numbers and then enter the meeting ID above and hit "#" or "##"
- Dial: 1 888 240 2560 (US or Canada only)
- or, List of International Numbers
- If connecting via Polycom unit:
- Dial 199.48.152.152 or bjn.vc
- Enter meeting ID above
- Use *4 to unmute
Slides
Talks can be deposited in the directory /group/halld/www/halldweb/html/talks/2015
on the JLab CUE. This directory is accessible from the web at https://halldweb.jlab.org/talks/2015/ .
Agenda
- Announcements
- Summary of Detector Performance
- Calibration Data Taking
- Subdetector Reports
- Simulations
- Calibration Processing
- AOB
Minutes
Attending: Sean (NU); Simon, Mark I., Kei, Elton, Justin, Eugene, Alex B., Nathan, Beni, Adesh, Matt S. (JLab); Curtis, Mike S., Will M., Naomi (CMU);
- Announcements
- There was a short meeting yesterday to discussing running this fall. Plans will be more clear by the Collaboration Meeting, but a certain number of standby shifts are being considered. It is not clear how much beam we will get (if any!).
- The next offline monitoring run will be launched this weekend.
- Summary of Detector Performance
- Curtis said that Matt had sent him some new materials, and the beamline and online groups are working to update their sections.
- Sean pointed out that efficiencies for several detectors need to be calculated.
- Calibration Data Taking
- Sean presented some preliminary numbers that he collected on how much more data is needed for a full, detailed calibration of all subdetectors. There was substantial discussion.
- Calorimeter estimates were refined to ~50M pi0's for the BCAL and 10-50M for the FCAL. Sean will follow up about more detailed estimates.
- Sean will perform some calculations to estimate running times needed.
- Subdetector Reports
- Simulations
- Mark submitted the first test jobs for the spring
- Sean will put together files for future simulations together and iterate with Mark.