Nov 10, 2008 Calorimetry
From GlueXWiki
NEW TIME Time: 11:15 ET.
- Phone:
- +1-800-377-8846 : US
- +1-888-276-7715 : Canada
- +1-302-709-8424 : International
- then enter participant code: 39527048# (remember the "#")
Contents
Items for followup from Oct 27 meeting
- Each subsystem must complete blanks in the Calibration Specification Table.
- Decision on Bcal sampling fraction needed if any changes are to be made to design.
- Resolution studies (Blake)
- Develop criteria for evaluating resolution studies
- Up-to-date geometry ONGOING.
- Decreased threshold for FM pmts. ONGOING
- Position resolution - understand dependence on granularity.
- Different segmentation for the outer section. - LOWER PRIORITY
- Study impact of inactive material at the end of Bcal on acceptance.
- Add F100 rad hard glass to simulation. - New graduate student has been assigned this project.
- Add roadmap for Bcal Roadmap to wiki (Elton)
Documents to Review
Tentative Agenda
- Announcements
- Calibration
- Progress on filling in the Calibration Specification Table.
- Fcal
- Report of timing studies with pmts and time calibration (Jake Bennet)
- Bcal
- Bcal readout
- Review of use of APDs for readout? (Serguei)
- Updates on resolution studies (Blake)
- have simulated pi0s in both geometries, have had compiling issues with analysis code the last week
- Bcal Construction
- Bcal readout
Minutes
Attending: