Winter 2024 Run
GEM-TRD detector test (March 11 - 14 2024)
Connect Information
To connect from the outside by phone please do the following
1.) To join via ZoomGov: connect Meeting ID: 160 199 0060 / Passcode 8394
2.) To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 660743227.
3.) To join via phone, use one of the following numbers and the Conference ID: 660743227.
4.) The moderator code is 8394
Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada
Specific instructions for connecting from JLab's Hall D conference room:
- Turn polycon on if necessary (do it before turning the computer on)
- With the polycon, place a call at 199.48.152.152
- Press # to enable the polycom keypad, then enter the meeting id: 660743227 and #
- You may have to unmute the microphone: #*4
- Turn the computer on if needed
Meeting General Agenda
Run planning meetings:
Beam and Hall configuration
- Experiment: Test
- Beam energy expected:
- 11.7 GeV
- Solenoid:
- OFF (Cooled at 80K)
- CW Beam:
- 250 MHz frequency ?.
- Range: 1-200 nA.
- Chopper slit: TBD (assume A or B, since Hall C will be at 4-pass)
- Standard current and radiators
- ~ TBD on 1.64 µm Al (1.86·10-5) amorphous radiator
- Position Slow Lock on or FFB on (FFB doesn't operate below 50nA).
- Radiators:
- Amorphous
- 1.64 µm Al (1.86·10-5 R.L., see study)
- 10 µm Al (11.2·10-5 R.L.)
- 30 µm Al (33.7·10-5 R.L.)
- Amorphous
- Tagger quadrupole on (-4.2 A). (Not necessary but as a check-out/good habit.)
- Collimator hole. Default running: 5.0 mm.
- Targets:
- H2 target. Warm empty cell
- PS converter: 750 µm
- PS test area: GEM-TRD detector
- Detectors:
- Off except Tagger hodoscope and PS.
General Information
This document describes the run plan for the Hall D Winter 2024 test-run.
- Schedule for the run (see Oct. 2023-May 2025 official schedule):
- March 11th-14th: 3 days for electron beam restoration, photon beam check-out and GEM-TRD test.
- Accelerator overall plan and priorities: Deliver physics beam to Hall C.
- Hall A: off (configuration change
- Halls B: off (configuration change
- Hall D plan
- Test GEM-TRD using the PS test area
- Expected Staffing and responsibilities:
- The Run Coordinator oversees the run:
- March - 11-14, 3 days: Alexandre Deur
- The Physics Division Liaison (PDL) and Hall D Work Coordinator/Safety Warden (S. Spiegel) verify that the proper safety rules are followed. PDL is:
- PDL: Benedikt Zihlmann
- Shifts: 1 person shifts: 1 local leader scheduler].
- The Run Coordinator oversees the run:
- Coordination Activities:
- The RC will attend the MCC meetings at 7:45am and 8:00am and the weekly MCC meeting (Wednesday, 1:30pm). The PDL will attend the weekly MCC meeting.
- Run meetings: broadcasted on Zoom. 8:45am in the counting house conference room. The Run Coordinator will be responsible for organizing and chairing the meeting.
- Useful links:
- Accelerator schedule and information
- Link to Richard Jones program to plot the beam profile at the collimator.
- Links to previous runplans
- Web-accessible EPICS information
- Links to beam parameters/radiation level monitoring:
- Last 8-hours plots showing 1-minute, 10-minute, and hourly averages
- Same but Last 24-hours
- Same but Last 72-hours
- Week, month, and quarter (3 months) plots also exist, with similar web addresses.
- A map of the radiation monitors
Runplan
- Make sure all radiators (from goni and amorphous ladder) are retracted. Active Col. in blocking position. Profiler retracted. Check that magnets are at their nominal fields.
- Verify electron beam quality (assume 1 day)
- Establish photon beam (assume 1 day).
- Ion Chambers trip threshold must be set using the 3 Al. radiators on amorphous radiator ladder)
- Tune electron beam with radiator retracted
- Radiator (amorphous and diamond) must be retracted. Collimator should be in blocking position.
- Typical levels are (for radiator retracted, collimator fully blocking, electron beam current 50 nA)
- RAD102_P1 ~ 10 mrad/hr (tagger area, gammas, between tagger and dump)
- RAD102_P2 ~30 mrad/hr (tagger area, gammas, on the ground below the goniometer).
- RAD102_P3 ~ 0.3 mrem/hr (tagger area, neutrons, near electronics racks)
- RAD508_P1 < 0.1 mrad/hr (collimator cave, gammas).
- RAD508_P2 ~ 0. mrad/hr (Hall. Neutrons).
- Typical levels are (for radiator retracted, collimator fully blocking, electron beam current 50 nA)
- Radiator (amorphous and diamond) must be retracted. Collimator should be in blocking position.
- Establish good photon beam
- Make sure tagger quadrupole is on and at -4.2 A. (It can be turned on only once the Hall is in power/beam permit.)
- Insert 2*10-5 RL radiator. Call MCC and ask to mask the FSD and turn off beam each time a radiator is moved
- Typical levels are (for 2×10-5 radiator, electron beam current 50 nA)
- RAD102_P1= 35 mrad/hr (tagger area, gammas, between tagger and dump)
- RAD102_P2= ~ 50 mrad/hr (tagger area, gammas, on the ground below the goniometer)
- RAD102_P3= ~2 mrem/hr (tagger area, neutrons, near electronics racks)
- RAD508_P1= ~10 mrad/hr (collimator cave, gammas).
- RAD508_P2 < ~ 0. mrad/hr (Hall. Neutrons).
- Typical levels are (for 2×10-5 radiator, electron beam current 50 nA)
- Insert 2*10-5 RL radiator. Call MCC and ask to mask the FSD and turn off beam each time a radiator is moved
- Verify beam position and envelope (Hovanes).
- Ask MCC to set beam position on 5C11b to x=-0.5 mm and y=+1.0 mm.
- Ask MCC for 5C11 and 5C11B HARP. Then do our radiator HARP scan, see instruction. If it looks good, proceed to next step. Otherwise, inform MCC.
- Insert profiler (no need for masking FSD when an object is inserted in the photon line), run with 1×10-4 radiator and 50 nA. Beam on the profiler should be at x=0.0±0.5cm; y=0.0±0.5cm. If not, inform MCC. Keep monitoring this position; produce a strip chart and log it.
- Radiation level study (1h):V
if you feel up to the task, strip chart the five radiation monitors (see above) and log them.- Run 5 min without radiator (Call MCC and ask to mask the FSD each time the radiator is moved). Beam current: 50nA. Repeat at 100 nA and 200 nA. There is no need to run the DAQ or stop the beam between each steps: the data are recorded by EPICS. However, the beam need to be off when moving to a different radiator for the next steps.
- Run 5 min with the 10-4 radiator (Call MCC). Beam current: 50nA. Repeat at 100 nA and 200 nA
- Run 3 min with the 3*10-4 radiator (Call MCC). Beam current: 50nA. Repeat at 100 nA and 200 nA
- Inform Richard Jones that we are getting ready to use the Active Collimator, and ask him if he needs to check the Active Collimator with the beam. ask richard whether profiler in or out
- Photon flux optimization and Active Collimator calibration. (1h).
Call Hovanes.(Requires confirmation from Richard about using the Active Collimator, see step above). the following steps will be done by Hovanes; solenoid should be on to protect FDC & CDC b/c collimator will be moved to 5 mm hole- re-Insert the 10-4 radiator (Call MCC). Use about 100 nA beam current. This will provide the Act. Col. nominal positions for its high gain values.
- Determine maximum photon beam transmission by doing 2D scans using the collimator x/y motions (Hovanes. 1h)
- Repeat procedure with 2*10-5 radiator (Call MCC) and 50 nA beam current. This will provide the Act. Col. nominal positions for its low gain values.
- Record on the white board what is the beam position on 5C11b and Active Collimator for optimal photon transmission, both for low and high Act. Col. gain.
- Until Hovanes determines to optimal 5C11b and Active Collimator position, keep profiler in and beam locked (MCC's duty) on the nominal 5C11b and x=0,y=0 profiler position. Once Active Collimator nominal beam position is known, retract profiler and lock the beam (MCC) on the active collimator.
- GEM-TRD test (Sergey Furletov, Lubomir Penchev)
- Standard configuration: 3.4×10-4 Al. radiator, TBD nA (50nA<I<200nA)
- Harp scan (30 min) near the end of the run? Or after significant beam interruptions requiring beam retuning?
Hall D situation room (current run plan)
Hall D counting room white board
Accelerator status
- Link to accelerator short term schedule (White board)
- Link to accelerator SAD calendar
- Bluejeans code for the daily MCC meetings and Wednesday 1:30 meeting: 569476853
Hot Checkout
To be completed by March. 10th??
0% ready ; 0% checked ; 100% not ready
Readiness for Winter 2024 run
- Target and most detectors to be masked.
- Surveys (Tim/Scott)
- Target
- Other?
- Beam line
- Collimator Motion (Hovanes).
- Active collimator detectors(Richard)
- Profiler (Hovanes)
- Luminosity monitor (=Active Target) (Hovanes).
- Halo monitors (Hovanes)
- Slow control (Hovanes).
- RF (Sergei)
- Radiation monitors (A. Deur)
- x-ray W shield (Tim/Lubomir/Justin).
- Detector systems
- RSAD and ESAD Safety documents (Lubomir/Beni):
- All documents are ready, signed and in the counting house.
- Today (01/10/2023 is the last day to read and sign the 2023 General Access Radiation Work Permit (RWP, SAF801kd) before access to the accelerator site is revoked
- RSAD link
- Hall D safety and training pages, with COVID-19 training requirement
- MedCon5 page
- JLab page giving staff and user COVID-19 training requirement
- Phones
- System experts should start looking for their phone and charger.
- System experts should have found their on-call phones by now and should start charging them.
- System experts should start carrying their (charged) phone.
- Hall Status/safety (Tim/Scott)
- Other topics?
Live Camera Feeds from the Four Counting Houses
- These feeds SHOULD be open and visible at all times from one of the monitors in each of the counting houses. (currently this is not working; we should post instructions how to establish this connection. J.R.)
- Management cautions AGAINST opening them from other locations or offsite, out of concern for available bandwidth.