Oct 1, 2009 Calorimetry
From GlueXWiki
Revision as of 14:56, 17 September 2009 by Elton (Talk | contribs) (→Items for followup from previous meeting(s))
Meeting will be dedicated to Calibration and Monitoring
Teleconference Time: 11:00 a.m. EST
- ESNET and EVO session
- Phone:
- +1-800-377-8846 : US
- +1-888-276-7715 : Canada
- +1-302-709-8424 : International
- then enter participant code: 77438230# (remember the "#"). Note: code changed 7/2/09
Contents
Items for followup from previous meeting(s)
- Two components fit for fiber attenuation (Zisis)
- Requirement of hardware gain matching of pmts for Fcal (and also Bcal)
- Fcal
- John iterating on support frame. Key load-bearing tubes, currenlty Al, could they switch to iron? Tim needs to weigh in on this one.
- Need to discuss strategy for fabrication of boards. Paul is concerned primarily about the HV board. We should include Fernando and Chris on the discussion for suggestion of production.
- Fastrack schedule: Matt asked if Fasttrack has a facility for "resource leveling". Does anyone know?
- Magnetic shield tests? (Tim needs to provide feedback)
- Eugene: Fcal activity on calibration is scheduled to start next month. We need to formally address it. Elton suggested creating a more realistic timeline for its implementation. Will discuss with project management and Eugene offline.
- Bcal
- Web page needs to be setup for communications. A mid-month report is also due. It can be information, but we need to keep consistent records. The site should be password protected.
- Bcal readout
- Elton to provide information on FM pmt cathode diameters.
- Slide 8: Matt Suggestion: Plot efficiency vs. a specific angle to understand behavior.
- Review decision on the orientation of FM pmt relative to Bfield, including tolerances due to expected field changes.
Documents to Review
Tentative Agenda
- Announcements
- Review of Action Items
- Calibration/Monitoring
- Fcal
- Bcal
- BCAL Readout
- Simulation
- Other business
Minutes
Attendees: