Nov 3-5, 2009 Calorimetry Backup
From GlueXWiki
BCAL Fabrication Readiness Review BACKUP
Contents
Contract Requirements
- Final Construction Plan
- Final Acceptance Test Plan
- Quality Assurance Plan.
Testing and Tracking: Section 5 of the Statement of Work
Testing
The vendor shall include a draft Acceptance Test Plan with their contract proposal with the final plan to be formally approved by JLab at the Readiness Review. The following items must be included:
- Acceptance of lead sheets upon receipt
- Acceptance of fibers upon receipt
- Acceptance of swaged lead sheets
- Acceptance of fibers during sorting
- Dimensional tests of aluminum base plates
- Dimensional tests of lead-scintillation matrix during stacking
- Acceptance of completed modules based on the following criteria:
- Dimensional testing of modules after machining
- Measurement of light transmission of completed modules.
- Determination of the uniformity of transmission across the face of the BCAL module, e.g. digital photos showing the number of damaged fibers.
- Measurements of the response of a sample of completed modules to cosmic rays.
Tracking
The vendor must keep a record (travelers) of all raw materials and inspections that are used in the construction of each module, and document the procedures followed during fabrication.