BCAL Fabrication Readiness Review BACKUP

Contract Requirements

  1. Final Construction Plan
  2. Final Acceptance Test Plan
  3. Quality Assurance Plan.

Testing and Tracking: Section 5 of the Statement of Work

Testing

The vendor shall include a draft Acceptance Test Plan with their contract proposal with the final plan to be formally approved by JLab at the Readiness Review. The following items must be included:

  1. Acceptance of lead sheets upon receipt
  2. Acceptance of fibers upon receipt
  3. Acceptance of swaged lead sheets
  4. Acceptance of fibers during sorting
  5. Dimensional tests of aluminum base plates
  6. Dimensional tests of lead-scintillation matrix during stacking
  7. Acceptance of completed modules based on the following criteria:
    1. Dimensional testing of modules after machining
    2. Measurement of light transmission of completed modules.
    3. Determination of the uniformity of transmission across the face of the BCAL module, e.g. digital photos showing the number of damaged fibers.
  8. Measurements of the response of a sample of completed modules to cosmic rays.

Tracking

The vendor must keep a record (travelers) of all raw materials and inspections that are used in the construction of each module, and document the procedures followed during fabrication.