Mar 18, 2010 Calorimetry
From GlueXWiki
Teleconference Time: 11:00 a.m. EST
- ESNET and EVO session
- Phone in CC F326 is 757-269-6337
- Phone in the Regina Videoconference Suite is 306-585-4204
- Phone only if requested:
- +1-800-377-8846 : US
- +1-888-276-7715 : Canada
- +1-302-709-8424 : International
- then enter participant code: 77438230# (remember the "#"). Phone line by request only.
Contents
Items for followup from previous meeting(s)
- Monitoring
- Matt to coordinate with Christina on the shipment of glass blocks and pmts/dividers for monitoring system test.
- Fcal
- Decision on rad hard detectors
- Check instability of FEU-84 pmt gains / finalize number / order additional FEU-84 pmts
Documents to Review
Tentative Agenda
- Announcements
- Review of Action Items
- Calibration/Monitoring
- FCAL
- Construction status
- Proceed with order of FEU-84 pmts?
- To shashlyk or not to shashlyk
- BCAL
- Construction Status
- Simulations
- Other Updates
Minutes
Attendees:
- BCAL Construction status
- Module 05 is up to 170 layers, Module 06 up to 130 layers.
- By March 24 Module 04 will be finished at RMS and so will be the go-no-go gauge for the alignment pins.
- On March 27 (Saturday) we are going to RMS to carry out the transmission uniformity tests for Modules 02-04 and go over all travellers.
- We hope to ship the modules to JLab just before or right after Easter weekend.
- Fibre tests (Shipment 10) are proceeding nominally.
- Lead tally is done, we need a teleconference (JLab-Regina) to decide on the quantity of lead for the last shipment and other logistics.