Agenda 060913
From GlueXWiki
Hi folks:
this is a reminder for our teleconference regarding the BCAL beam tests at Hall-B on Wednesday September 13 at 12:30 EDT.
Connection
Call (306) 781-5999
Participants' code 3472000#
Agenda
- Business Arising
- Action Items (see updated list below)
- Hall-B
- Status Quo and Progress (see Beam_Test_Hardware)
- Electronics, Cabling, Trigger see Beam_Test_Hardware, Beam Test Cabling and Beam_Test_Trigger_and_electronics)
- DAQ, Online
- Cosmics runs
- Run Plan (see Beam_Test_Run_Plan)
- Monte Carlo (see Beam_Test_Software)
- Any other business
- Offline team. Analysis plan, data transfer and macros.
Action Items
- BPM, Veto: Slow control cables and stand construction pending.
- Light Leak: Light leak test pending in alcove.
- Tagger, Trigger, Cables: The fast core cable is pending.
- Data storage/Silo Request: David and Zisis will deal with this offline.
- Online Macros/MC Data steam/MC Validation & Binning: David and Zisis will work on these.
- Run Plan: Decide on position/angle configurations and priorities.