Solenoid Coil Test Weekly Meeting
Location and Time
- Thu 30-Sep-2010 9:30am ARC 428
Agenda
- Installation status
- vapor-cooled lead connections?
- what's left?
- when do we give two weeks notice to Errol?
- Aftermath of DOE review 28-Sep - George, Elliott
- can we detect turn-to-turn shorts?
- pulse reflection in coil
- subcoil voltages
- Hall probe
- can we detect turn-to-turn shorts?
- Conduct of Operations - Josh, Elliott
- status of creating documents
- OSP documents and review - Elliott, George
- what is left to do?
- when can/must we turn everything in?
- Do we need He vessel LHe level in interlock system - Hovanes, Yi, Elliott
- Test plan - Josh
- addition of check valve and relief valve in lead flow system
- Magnet power supply and interlock commissioning - Mark
- latest status
- adding a shunt to the interlock system
- adding ground fault detection
- Controls racks - Scot
- strain gauge interlock
- UPS interlock
- anything else?
- PLC programming/testing status - Mark W
- UPS interlock
- guard shack
- what's left?
- backup PLC programmer, file locations, license key
- tutorial?
- EPICS <--> PLC communications - Hovanes
- PV list from Jonathan Creel and PLC tags
- connection to guard shack
- under what circumstances do we notify the guard shack?
- HMI and EWEB programming - Yi, Hovanes
- current status
- tutorial?
- Coil repair status - George
- Solenoid review 25-26 Oct
- Preparations for testing next coil - George, Elliott
- update P&I
- splices
- yoke location
- piping adaptors
- downstream yoke spacers
- controls racks rewiring