Nov 10, 2011 SiPM Electrical and Cooling
From GlueXWiki
Revision as of 17:45, 3 November 2011 by Elton (Talk | contribs) (→Action Items from previous meetings)
Action Items from previous meetings
- Verify location of standoffs for circuit board. (Fernando)
- Location and room for UFL connector for thermistor needs to be finalized. (Chris and Jim)
- Jack to update board with bias compensation circuitry (Jack)
- The RTDs will need a controller. Scot will see if Hall D has an existing one that can be used; otherwise one will be ordered.
Tentative Agenda
- Announcements
- Action Items
- Schedule, reporting, and manpower (Elton)
- SiPM production testing (everyone)
- Light source / optics
- Electronic boards
- Cabling
- Cooling plate
- Programming
- Other?
- SiPM testing (Ivan)
- Mechanical assembly (Scot)
- Mechanical (Jim)
- Mechanical drawings (Chuck)
- Temperature compensation (Jack)
- Preamp-summing (Fernando)
Minutes
Attending: