Action Items from previous meetings
-
Develop front and back views of jumper sheets. (Jack)- This specifically includes the settings for the pre-production boards that are needed by Wed of next week.
- Test wrapping forms (Elton)
-
Order glue (and any other consumables) to glue light guides (Scot) -
Check new gluing jig for the light guides (Scot and Jim)
Tentative Agenda
- Announcements
- Action Items
- Schedule, reporting, and manpower (Elton)
- SiPM production testing (everyone)
- SiPMs assignment for new boards
- Mechanical assembly (Jim)
- Temperature compensation (Jack)
- Electronic boards (Chris)
- Light guide gluing setup (Scot via e-mail)
- I have completed the redesigned light guide "push" vacuum wand / base fabrication as of 1:30 p.m. today.
- I ordered a 1 LB. bottle of Norland NOA 87 light guide UV adhesive on 08/17/2012 - PR # 321682
Minutes
Attending:
Tentative Agenda
- Announcements
- Action Items
- Schedule, reporting, and manpower (Elton)
- SiPM production testing (everyone)
- SiPMs assignment for new boards
- Mechanical assembly (Jim)
- Temperature compensation (Jack)
- Electronic boards (Chris)
- Light guide gluing setup (Scot via e-mail)
- I have completed the redesigned light guide "push" vacuum wand / base fabrication as of 1:30 p.m. today.
- I ordered a 1 LB. bottle of Norland NOA 87 light guide UV adhesive on 08/17/2012 - PR # 321682