November 30, 2015

From GlueXWiki
Revision as of 17:26, 10 December 2015 by Somov (Talk | contribs)

Jump to: navigation, search
  • Modifications of config files
- parameters for CAEN R-C adjustment
- parameters for fa125 initialization
- implementation of SYNC events (in progress)
- configuration of TRD, concurrent running with ST (in progress)
  • Other
- new TS firmware (check in progress)
- BCAL LED trigger distribution through TS
- TPOL stand alone self-trigger with CTP


  • L1 trigger commissioning plans for the fall run
  • PS trigger (TAGM bias voltage calibration, TAGH voltage scans). Run TRD in parallel, if no problems.
- test/debug trigger (2 - 3 hours).
- production (1 - 2 night shifts)
run conditions depend on the accelerator performance (200 nA electron current, 10^-4 radiator, 10^-3 converter + Be converter)
  • Debug trigger for FCAL MIPS (ST?TOF)
  • Debug trigger for FDC alignment (ST/TOF + FCAL)
test/debug trigger (3 - 4 hours)
production at low luminosity with FDC switched on (1 - 2 night shifts)
  • Debug FCAL/BCAL trigger
- test/debug trigger (3 - 4 hours)
- take data with the BCAL/FCAL trigger (1 - 2 night shifts). FCAL/BCAL thresholds will be tuned.
- test high rate trigger performance. Take data with 'nominal' trigger thresholds.
  • - Trigger generated by TAGM/TAGH


- Requests from sub-detectors