2017 mcsmear Workplan

From GlueXWiki
Revision as of 12:32, 21 June 2017 by Sdobbs (Talk | contribs) (FCAL)

Jump to: navigation, search

Timeline Goals

Simulation Tuning

  • August 1 -- Review of status
  • Sept. 1 -- Smearing updates finished, testing begins
  • Sept. 15 -- Ready for simulation campaign

Job Submission

  • August 1 -- Richard successfully runs jobs on most OSG nodes
  • Sept. 1 -- Mark I. completes knowledge transfer from Richard, submits jobs in production framework
  • Sept 15 -- Ready for simulation campaign


Work Projects

  • red - Project assigned but not begun
  • yellow - In progress
  • green - Finished


BCAL

Project Person Status Presentations
Match shower energy resolutions
Match shower timing resolutions
Match hit efficiencies / bad channels
Match shower efficiencies

CDC / FDC

Project Person Status Presentations
Match CDC hit timing [CDC/cdc_drift_table and CDC/cdc_drift_parms] Naomi J. June, 14
Match CDC hit integrals Naomi J. June, 14
Update CDC hit thresholds
Update FDC hit thresholds
Update CDC dead channels
Update FDC dead channels
Update track efficiencies
Update track resolutions

FCAL

Project Person Status Presentations
Update bad channels
Match shower energy resolutions
Match shower timing resolutions

SC

Project Person Status Presentations
Match hit timing resolutions
Match hit efficiencies

TOF

Project Person Status Presentations
Match hit timing resolutions
Match hit efficiencies

ANALYSIS

Project Person Status Presentations
Match shower energy resolutions
Match shower timing resolutions


Software

Project Person Status Presentations
Deploy GlueX software on OSG and successfully run simulation jobs Richard J.
Modify simulation workflow software to work on OSG Mark I.