Difference between revisions of "2020 Winter - 2021 Spring"

From GlueXWiki
Jump to: navigation, search
(Hall work)
Line 1: Line 1:
 
= Hall work =
 
= Hall work =
#* Water level sensor installation  
+
# Water level sensor installation  
#**Total:  2 days. 1 day testing + 1 day installation
+
#*Total:  2 days. 1 day testing + 1 day installation
#* Darkening leak check  
+
# Darkening leak check  
#** Total: 1 day
+
#* Total: 1 day
#* Modification on vent exit to reduce FPGA temperature  
+
# Modification on vent exit to reduce FPGA temperature  
#** Total: 3 days. 1 day diagnose, 1 day test and 1 day installation. Excluding time for designing time.
+
#* Total: 3 days. 1 day diagnose, 1 day test and 1 day installation. Excluding time for designing time.
#* DIRC Diffuser seal issue  
+
# DIRC Diffuser seal issue  
#** Total: 2 days. 1 day test and 1 day installation. Excluding time for water seal test
+
#* Total: 2 days. 1 day test and 1 day installation. Excluding time for water seal test
#* Contaminated mirror replacement in north upper OB  
+
# Contaminated mirror replacement in north upper OB  
#** Total: 1 days. Uninstall + Disassembly: 1 day; mirror removal + setting up clean area, mirror gluing+ curing: 3 days; silicone seal +  cleaning + assembly: 1 days; installation: 1 day. Excluding time for water seal test
+
#* Total: 1 days. Uninstall + Disassembly: 1 day; mirror removal + setting up clean area, mirror gluing+ curing: 3 days; silicone seal +  cleaning + assembly: 1 days; installation: 1 day. Excluding time for water seal test
#* Inspect the south lower OB  
+
# Inspect the south lower OB  
#** 1 day
+
#* 1 day
#** If mirror problem, adding 6 more days for mirror replacement.  
+
#* If mirror problem, adding 6 more days for mirror replacement.  
#* South box module c2r18 over current limit diagnosis work
+
# South box module c2r18 over current limit diagnosis work
 +
 
 
= Non Hall Work =
 
= Non Hall Work =
 
#* Testing spare DIRC modules
 
#* Testing spare DIRC modules

Revision as of 12:32, 28 August 2020

Hall work

  1. Water level sensor installation
    • Total: 2 days. 1 day testing + 1 day installation
  2. Darkening leak check
    • Total: 1 day
  3. Modification on vent exit to reduce FPGA temperature
    • Total: 3 days. 1 day diagnose, 1 day test and 1 day installation. Excluding time for designing time.
  4. DIRC Diffuser seal issue
    • Total: 2 days. 1 day test and 1 day installation. Excluding time for water seal test
  5. Contaminated mirror replacement in north upper OB
    • Total: 1 days. Uninstall + Disassembly: 1 day; mirror removal + setting up clean area, mirror gluing+ curing: 3 days; silicone seal + cleaning + assembly: 1 days; installation: 1 day. Excluding time for water seal test
  6. Inspect the south lower OB
    • 1 day
    • If mirror problem, adding 6 more days for mirror replacement.
  7. South box module c2r18 over current limit diagnosis work

Non Hall Work

    • Testing spare DIRC modules
    • Control and operation
      • Alarm modification strategy
      • Resolving (double checking) DIRC hole in occupancy before run starts
      • Dis-entangle DIRC interlock and interlock reset from FCAL and CCOM
      • Individual (stand alone) SiPM TDA offset
    • Tile FPGA voltage regulation issue.
    • Recover loan-out (Duke SOLID group) MOROC chips

Not-to-forget items

    • Re-activate tile-temperature alarm for the south box c2r18
    • Including south box c2r18 fiber verification back into the DAQ starting procedure