# Hall work:
+
= Hall work =
 
#* Water level sensor installation  
 
#* Water level sensor installation  
 
#**Total:  2 days. 1 day testing + 1 day installation
 
#**Total:  2 days. 1 day testing + 1 day installation
Line 14: Line 14:
 
#** If mirror problem, adding 6 more days for mirror replacement.  
 
#** If mirror problem, adding 6 more days for mirror replacement.  
 
#* South box module c2r18 over current limit diagnosis work
 
#* South box module c2r18 over current limit diagnosis work
# Non Hall Work:
+
= Non Hall Work =
 
#* Testing spare DIRC modules
 
#* Testing spare DIRC modules
 
#* Control and operation
 
#* Control and operation
Line 23: Line 23:
 
#* Tile FPGA voltage regulation issue.
 
#* Tile FPGA voltage regulation issue.
 
#* Recover loan-out (Duke SOLID group) MOROC chips
 
#* Recover loan-out (Duke SOLID group) MOROC chips
# Not-to-forget items:
+
= Not-to-forget items =
 
#* Re-activate tile-temperature alarm for the south box c2r18
 
#* Re-activate tile-temperature alarm for the south box c2r18
 
#* Including south box c2r18 fiber verification back into the DAQ starting procedure
 
#* Including south box c2r18 fiber verification back into the DAQ starting procedure

Revision as of 12:31, 28 August 2020

Hall work

    • Water level sensor installation
      • Total: 2 days. 1 day testing + 1 day installation
    • Darkening leak check
      • Total: 1 day
    • Modification on vent exit to reduce FPGA temperature
      • Total: 3 days. 1 day diagnose, 1 day test and 1 day installation. Excluding time for designing time.
    • DIRC Diffuser seal issue
      • Total: 2 days. 1 day test and 1 day installation. Excluding time for water seal test
    • Contaminated mirror replacement in north upper OB
      • Total: 1 days. Uninstall + Disassembly: 1 day; mirror removal + setting up clean area, mirror gluing+ curing: 3 days; silicone seal + cleaning + assembly: 1 days; installation: 1 day. Excluding time for water seal test
    • Inspect the south lower OB
      • 1 day
      • If mirror problem, adding 6 more days for mirror replacement.
    • South box module c2r18 over current limit diagnosis work

Non Hall Work

    • Testing spare DIRC modules
    • Control and operation
      • Alarm modification strategy
      • Resolving (double checking) DIRC hole in occupancy before run starts
      • Dis-entangle DIRC interlock and interlock reset from FCAL and CCOM
      • Individual (stand alone) SiPM TDA offset
    • Tile FPGA voltage regulation issue.
    • Recover loan-out (Duke SOLID group) MOROC chips

Not-to-forget items

    • Re-activate tile-temperature alarm for the south box c2r18
    • Including south box c2r18 fiber verification back into the DAQ starting procedure