Hall work

  1. Water level sensor installation
    • Total: 2 days. 1 day testing + 1 day installation
  2. Darkening leak check
    • Total: 1 day
  3. Modification on vent exit to reduce FPGA temperature
    • Total: 3 days. 1 day diagnose, 1 day test and 1 day installation. Excluding time for designing time.
  4. DIRC Diffuser seal issue
    • Total: 2 days. 1 day test and 1 day installation. Excluding time for water seal test
  5. Contaminated mirror replacement in north upper OB
    • Total: 1 days. Uninstall + Disassembly: 1 day; mirror removal + setting up clean area, mirror gluing+ curing: 3 days; silicone seal + cleaning + assembly: 1 days; installation: 1 day. Excluding time for water seal test
  6. Inspect the south lower OB
    • 1 day
    • If mirror problem, adding 6 more days for mirror replacement.
  7. South box module c2r18 over current limit diagnosis work

Non Hall Work

  1. Testing spare DIRC modules
  2. Control and operation
    • Alarm modification strategy
    • Resolving (double checking) DIRC hole in occupancy before run starts
    • Dis-entangle DIRC interlock and interlock reset from FCAL and CCOM
    • Individual (stand alone) SiPM TDA offset
  3. Tile FPGA voltage regulation issue.
  4. Recover loan-out (Duke SOLID group) MOROC chips

Not-to-forget items

    • Re-activate tile-temperature alarm for the south box c2r18
    • Including south box c2r18 fiber verification back into the DAQ starting procedure