Apr 12, 2013 Design Meeting
From GlueXWiki
Friday April 12,2013 at 8:15am At Jefferson Lab, the meeting will be held in room ARC 428
Agenda
- ESH&Q minutes - Media:pressure safety.pdf
- Announcements
- Temple review earlier this week
- Lehman review May 7
- Still looking for 1st beam in hall D April 2014
- Upstream platform 1" high
- NX - any hour now.....
- Bill - Tagger install
- George/Floyd - Solenoid/Magnet mapping
- Jim/James - BCAL cooling/Target
- Rich - FDC cable management
- Remaining work
- Solenoid power up - #1 priority - expected date - April, 2013
Useful Info
- Schedule M:\halld_engineering\Presentations
- pics M:\PhyCoord\cameras\halldcam3
- Schedule M:\halld\Individual-Schedules\Installation
- Engineering tasks M:\halld_engineering\Manpower-schedule
- Engineering tools folder M:\halld_engineering\engineering tools