Apr 29, 2010 Calorimetry

From GlueXWiki
Revision as of 13:24, 15 April 2010 by Elton (Talk | contribs) (Items for followup from previous meeting(s))

Jump to: navigation, search

Teleconference Time: 11:00 a.m. EDT

  • ESNET and EVO session
  • Phone in CC F326 is 757-269-6337
  • Phone in the Regina Videoconference Suite is 306-585-4204
  • Phone only if requested:
    • +1-800-377-8846 : US
    • +1-888-276-7715 : Canada
    • +1-302-709-8424 : International
    • then enter participant code: 77438230# (remember the "#"). Phone line by request only.

Items for followup from previous meeting(s)

  1. Monitoring
    • Bcal: Testing to see if LED sources can be viewed by pmts on both sides of the module (UofR).
  2. Fcal
    • Draft agenda for Readiness Review (Elton and Matt)
    • Decision on rad hard detectors

Table of Options DRAFT

Configurations for Fcal calorimter insert, assume sigma/E = c1/sqrt(E) + c2 + c3
Configuration Block Size (mm2) Length(MM) X0 (mm) Sum X0 Delta SC (mm) Delta Pb (mm) c1 c2 c3
Pb glass F8-00 40x40 40 31 12.9 - - 7.4? 3.6? 0
Pb glass F108 40x40 40 31? 12.9 - -  ?  ? 0
Shashlyk COMPAS 38x38 500 (392) 15.6 25 1.5 0.8 6 0 0
Shashlyk KOPIO PMT 110x110 525 34 15 1.5 0.25 3.59 1.1 0.9
Shashlyk KOPIO APD 110x110 525 34 15 1.5 0.25 2.77 1.7 0.27
PbWO4 PRIMEX 20.5x20.5 180 8.9 20 - - 2.6 - -

See Property Table from Eugene

Tentative Agenda

  1. Announcements
  2. Review of Action Items
  3. Calibration/Monitoring
  4. FCAL
    1. Construction status
    2. Readiness Review
    3. To shashlyk or not to shashlyk. Options (Elton) see Table.
  5. BCAL
    1. Construction Status
    2. Responsibility for BCAL reconstruction software
      • David Lawrence's talk at the April 6 Offline Meeting. Slide 2 summarizes history of BCAL reconstruction.
  6. Simulations
  7. Other Updates

Minutes

Attendees: