Apr 29, 2010 Calorimetry

From GlueXWiki
Revision as of 09:28, 29 April 2010 by Zihlmann (Talk | contribs) (Table of Options DRAFT)

Jump to: navigation, search

Teleconference Time: 11:00 a.m. EDT

  • ESNET and EVO session
  • Phone in CC F326 is 757-269-6337
  • Phone in the Regina Videoconference Suite is 306-585-4204
  • Phone only if requested:
    • +1-800-377-8846 : US
    • +1-888-276-7715 : Canada
    • +1-302-709-8424 : International
    • then enter participant code: 77438230# (remember the "#"). Phone line by request only.

Items for followup from previous meeting(s)

  1. Monitoring
    • Bcal: Testing to see if LED sources can be viewed by pmts on both sides of the module (UofR).
  2. Fcal
    • Draft agenda for Readiness Review (Elton and Matt)
    • Decision on rad hard detectors
  3. Bcal
    • Send copy of contract with Ross to JLab
    • Report on beam test data at small incidence angles.

Table of Options DRAFT

Configurations for Fcal calorimter insert, assume sigma/E = c1/sqrt(E) + c2 + c3
Configuration Block Size (mm2) Length(MM) X0 (mm) Sum X0 Delta SC (mm) Delta Pb (mm) c1 c2 c3
Pb glass F8-00 40x40 400 31 12.9 - - 7.4? 3.6? 0
Pb glass F108 40x40 400 31? 12.9 - -  ?  ? 0
Shashlyk COMPAS 38x38 500 (392) 15.6 25 1.5 0.8 6 0 0
Shashlyk KOPIO PMT 110x110 525 34 15 1.5 0.25 3.59 1.1 0.9
Shashlyk KOPIO APD 110x110 525 34 15 1.5 0.25 2.77 1.7 0.27
PbWO4 PRIMEX 20.5x20.5 180 8.9 20 - - 2.6 - -

See Property Table from Eugene

Tentative Agenda

  1. Announcements
  2. Review of Action Items
  3. Calibration/Monitoring
  4. FCAL
    1. Construction status
    2. Readiness Review
    3. To shashlyk or not to shashlyk. Options (Elton) see Table. Physics Impact, see GlueX-doc-1481
  5. BCAL
    1. Construction Status
  6. Simulations
  7. Other Updates

Minutes

Attendees: