(Created page with "== Meeting Time and Place == Thursday April 08, 2021, 3:30pm Bluejeans https://bluejeans.com/465620466 * Present - Elton, Dave, Stephanie, Ilya, Rory, Mark S, Beni, Simon, Ma...")
 
(Minutes and Action Items)
 
(5 intermediate revisions by the same user not shown)
Line 6: Line 6:
  
 
== Agenda ==
 
== Agenda ==
* Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/February_25,_2021_CPP_Design_Meeting/ERR_discussion
+
* Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/March_25,_2021_CPP_Design_Meeting    
* Readiness Review Report
+
* Microscope move
** [[Media:CPP_ERR_Report.pdf]]
+
** https://halldweb.jlab.org/doc-private/DocDB/ShowDocument?docid=4972
** [[CPP and NPP Readiness Review]]
+
 
* Lead Configuration
 
* Lead Configuration
 
** [[Media:Lead_joints.pdf]]
 
** [[Media:Lead_joints.pdf]]
 
** [[Media:Lead_joint_side.pdf]]
 
** [[Media:Lead_joint_side.pdf]]
* MWPC Issues
+
* Do we need new gas system? Not using CDC gas?
** [[Media:MWPC_issues.pdf]]         
+
** Can CDC use 90/10 for veto? (Naomi)
* Microscope move
+
** Can we use CMU gas mixing system?
** [[Media:Microscope_Move.pdf]]
+
** [[Media:Microscope_Location.pdf]]
+
 
* Design/Fab/Procurement status
 
* Design/Fab/Procurement status
 
** Stand
 
** Stand
Line 33: Line 30:
  
 
== Minutes and Action Items ==
 
== Minutes and Action Items ==
* James to make parts for Microscope new location by end of June
+
* Discussed location of Microscope - Tim to check to make sure Micro stand can straddle vacuum support. It turns out it should be no problem
* Tim to re-measure distance Microscope can move DS
+
* Discussed being able to move the racks and that we have adequate cable length - Tim checked with Chris Stanislav - appears ok
* Ilya stated that the 45° joint in the lead absorber is not an issue. He will have a closer look at the 90° joints
+
* Ilya looked at 90 degree joints in lead shield where there is 1/2 inch of steel - turns out ok, but should machine edge so there are no gaps.
* Need to machine the steel on the 90° joints of the lead absorber so there are no gaps
+
* It was decided that the CDC will be used during the experiment so we will need a separate gas system for the CPP. We discussed a completely new mixing tank, pre-mixed bottles or borrowing from CMU
* Tim (Stephanie)to send Beni US moveable lead shield configuration
+
* Move meeting to 3:30 and add Beni
+

Latest revision as of 07:50, 22 April 2021

Meeting Time and Place

Thursday April 08, 2021, 3:30pm Bluejeans https://bluejeans.com/465620466

  • Present - Elton, Dave, Stephanie, Ilya, Rory, Mark S, Beni, Simon, Mark I

Agenda

Minutes and Action Items

  • Discussed location of Microscope - Tim to check to make sure Micro stand can straddle vacuum support. It turns out it should be no problem
  • Discussed being able to move the racks and that we have adequate cable length - Tim checked with Chris Stanislav - appears ok
  • Ilya looked at 90 degree joints in lead shield where there is 1/2 inch of steel - turns out ok, but should machine edge so there are no gaps.
  • It was decided that the CDC will be used during the experiment so we will need a separate gas system for the CPP. We discussed a completely new mixing tank, pre-mixed bottles or borrowing from CMU