Difference between revisions of "April 08, 2021 CPP Design Meeting"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
Line 13: | Line 13: | ||
** [[Media:Lead_joint_side.pdf]] | ** [[Media:Lead_joint_side.pdf]] | ||
* Do we need new gas system? Not using CDC gas? | * Do we need new gas system? Not using CDC gas? | ||
− | ** Can CDC use 90/ | + | ** Can CDC use 90/10 for veto? (Naomi) |
** Can we use CMU gas mixing system? | ** Can we use CMU gas mixing system? | ||
* Design/Fab/Procurement status | * Design/Fab/Procurement status |
Revision as of 16:27, 8 April 2021
Meeting Time and Place
Thursday April 08, 2021, 3:30pm Bluejeans https://bluejeans.com/465620466
- Present - Elton, Dave, Stephanie, Ilya, Rory, Mark S, Beni, Simon, Mark I
Agenda
- Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/March_25,_2021_CPP_Design_Meeting
- Microscope move
- Lead Configuration
- Do we need new gas system? Not using CDC gas?
- Can CDC use 90/10 for veto? (Naomi)
- Can we use CMU gas mixing system?
- Design/Fab/Procurement status
- Stand
- Steel
- Fcal platform mods
- Things to work out
- Gas line manifold/bubblers (Beni has some)
- Complete structural analysis
- Develop Detailed installation plan
- Develop Design/operational/Maintenance Requirements
- Modified US vacuum system
- Solid target installation
- Documentation for ERR
- Microscope move