(Created page with "== Action Items from previous meetings == # Determine if swapped bias pins was accidental or in design (Chris) # Develop front and back views of jumper sheets. Also get latest v...")
 
(Action Items from previous meetings)
Line 5: Line 5:
 
# Request Hamamatsu data sheets from Chile to be used as input to jumper settings for boards (Elton)
 
# Request Hamamatsu data sheets from Chile to be used as input to jumper settings for boards (Elton)
 
# <strike> Double-check that the jumper settings for #37 (U-board counting) are correct (Jack) </strike>
 
# <strike> Double-check that the jumper settings for #37 (U-board counting) are correct (Jack) </strike>
 +
# Provide section views of board to Fernando (Jim)
 +
# Run temperature configuration for cooling plate with new geometry (Jim)
  
 
== Tentative Agenda ==
 
== Tentative Agenda ==

Revision as of 16:54, 29 March 2012

Action Items from previous meetings

  1. Determine if swapped bias pins was accidental or in design (Chris)
  2. Develop front and back views of jumper sheets. Also get latest version of drawings (Jack)
  3. Request Hamamatsu data sheets from Chile to be used as input to jumper settings for boards (Elton)
  4. Double-check that the jumper settings for #37 (U-board counting) are correct (Jack)
  5. Provide section views of board to Fernando (Jim)
  6. Run temperature configuration for cooling plate with new geometry (Jim)

Tentative Agenda

  1. Announcements
  2. Action Items
  3. Schedule, reporting, and manpower (Elton)
  4. SiPM production testing (everyone)
  5. Mechanical assembly (Scot)
  6. Mechanical (Jim)
  7. Mechanical drawings (Chuck)
  8. Temperature compensation (Jack)
  9. Preamp-summing (Chris)