Revision as of 07:48, 15 April 2011

Meeting Time and Place

Friday April 15, 2011 at 8:15am At Jefferson Lab, the meeting will be held in room ARC 231

Agenda

  • ESH&Q minute - Hall D AHA
  • Announcements - FDC Review, Collab mtg
    • training -
    • Manpower
    • Space
    • Budgets
    • Taxes
  • Solenoid Test Status *
  • FDC construction update
  • CAD update
  • Upcoming work
    • FDC Production** Solenoid coil 3 test
    • solenoid coil 2 repair
    • solenoid coil 2 test
    • Collimator cave pedestal install
    • Upstream Platform install
    • BCAL wedge inspection
    • BCAL readout prototype
    • LCW installation
    • Hall D cryogenics design
    • Solenoid steel design/Fab
    • Solenoid installation into Hall D
    • BCAL assembly tooling design
    • FCAL Platform Design
    • Beamline vacuum design/fab/install
    • Pair spec magnet modification

Outstanding Action Items

  • need to get dipole (for sweep magnet) from FEL - Jim Coleman
  • need to look at organizing someone to take care of material handling for Hall D. Can we use the transportainer?
  • check to see if we can get a MS project group license - Tim
  • Review upstream platform tie offs, fork maneuver, As builts. rail heights

Discussions

    • In attendance W. Crahen, J. Fochtman, C. Hutton, V. Razmyslovich, J. Lagner, F. Martin, R. Getz, C. Heck, D. Butler, W. Sachleben, A. Johnson, G. Biallas, T. Carstens, Tim Whitlatch