* Trigger Commissioning Plan
 +
:# Integrate PS trigger to the global DAQ (1 - 2 days)
 +
:# Tune trigger parameters (trigger threshold scans, tune timing offsets) and study performance for
 +
::: - FCAL  (2 days)
 +
::::  Performed threshold scans for noise/cosmic runs [[https://logbooks.jlab.org/entry/3328066 Log entry]]
 +
::: - BCAL  (1 day)
 +
::: - FCAL & BCAL (1 day)
 +
::: - ST and TOF (1 day)
 +
::: - Coincidence of FCAL/BCAL and ST/TOF (2 days)
 +
::: - Multiple triggers in the system  (2-3 days)
 +
:::: Trigger hit-pattern is written to the trigger record
  
 +
*Trigger Monitoring
 +
 +
: [[Media:trig_gui.png | Trigger Rates]]
 +
 +
: [[Media:fcal_scalers.png | Sub-detector scalers]]
 +
 +
:: - Use config files to initialize electronics modules

Revision as of 09:39, 6 April 2015

  • Trigger Commissioning Plan
  1. Integrate PS trigger to the global DAQ (1 - 2 days)
  2. Tune trigger parameters (trigger threshold scans, tune timing offsets) and study performance for
- FCAL (2 days)
Performed threshold scans for noise/cosmic runs [Log entry]
- BCAL (1 day)
- FCAL & BCAL (1 day)
- ST and TOF (1 day)
- Coincidence of FCAL/BCAL and ST/TOF (2 days)
- Multiple triggers in the system (2-3 days)
Trigger hit-pattern is written to the trigger record
  • Trigger Monitoring
Trigger Rates
Sub-detector scalers
- Use config files to initialize electronics modules