Difference between revisions of "Aug 23, 2011 SiPM Electrical and Cooling"

From GlueXWiki
Jump to: navigation, search
(Action Items from previous meetings)
Line 14: Line 14:
 
# Mechanical assembly (Jim)
 
# Mechanical assembly (Jim)
 
# Temperature compensation (Jack)
 
# Temperature compensation (Jack)
# Electronic boards (Chris)
+
# Electronic boards (Fernando and Chris)
# Light guide gluing setup (Scot via e-mail)
+
# Light guide gluing setup  
  
 
== Minutes ==
 
== Minutes ==
 
''Attending:
 
''Attending:

Revision as of 07:47, 23 August 2012

Action Items from previous meetings

  1. Decide on cable connections for monitoring cable from Bcal wedge to patch panel. Consider electronics needed for pulsing system (Elton and Fernando)
  2. Clarify option of purchase of additional SiPMs (Elton)
  3. Send optional values for 86KOHm resistor to Chris to investigate delivery times (Jack and Chris)
  4. Order micro Dsub connectors to make connections to the monitoring control board (Chris)

Tentative Agenda

  1. Announcements
  2. Action Items
  3. Schedule, reporting, and manpower (Elton)
  4. SiPM production testing (Yi)
  5. Mechanical assembly (Jim)
  6. Temperature compensation (Jack)
  7. Electronic boards (Fernando and Chris)
  8. Light guide gluing setup

Minutes

Attending: