Aug 23, 2011 SiPM Electrical and Cooling

From GlueXWiki
Revision as of 16:57, 16 August 2012 by Elton (Talk | contribs) (Action Items from previous meetings)

Jump to: navigation, search

Action Items from previous meetings

  1. Decide on cable connections for monitoring cable from Bcal wedge to patch panel. Consider electronics needed for pulsing system (Elton and Fernando)
  2. Clarify option of purchase of additional SiPMs (Elton)
  3. Send optional values for 86KOHm resistor to Chris to investigate delivery times (Jack and Chris)
  4. Order micro Dsub connectors to make connections to the monitoring control board (Chris)

Tentative Agenda

  1. Announcements
  2. Action Items
  3. Schedule, reporting, and manpower (Elton)
  4. SiPM production testing (Yi)
  5. Mechanical assembly (Jim)
  6. Temperature compensation (Jack)
  7. Electronic boards (Chris)
  8. Light guide gluing setup (Scot via e-mail)

Minutes

Attending: