  1. Comments from Tuesday's meeting
    • Issue of optical isolation between pmts has been settled (crosstalk). There is no apparent cross talk.
  2. Schedule (Hall-B Schedule)
  3. Cart
    • Cart is scheduled for pickup on Sept 16, arrival at JLab on Monday Aug 21
    • The cart will be load tested with a 25% overload. The tests will cover all the motions expected during operation, including extreme positions. The limit switches are being tested today (separately). Dave Kashy raised a concern about a single wheel on the far support point, especially related to torques generated during direction adjustment of the wheels. This will be watched closely during the cart load test.
  4. Module
    • The test module will be shipped out on 13th, arrival at JLab on 21. The rotators, fabricated out of wood, will be reviewed upon arrival by Dave Kashy.
  5. Hall B
    • Hall-B (platform)
    • Platform is assembled and being installed in the hall. Survey will be requested once the area is ready. These activities should be completed next week. The catwalk is in the machine shop and delivery schedule will be checked.
    • Travel on schedule
  6. DAQ status
    • David reported on the status of the DAQ. One of four crates is presently being readout. The crate for the calorimeter will be checked out next, then the two tagger crates.
    • Dave, Elton and Dan reviewed the complete list of cables last Friday and missing cables are being identified or made.